A 36-acre, Costco-anchored retail center in northwest Bakersfield is in environmental review. Here is what is proposed, what came before it and what it signals for the local retail market.

The 7th Standard Marketplace Costco would anchor a proposed 225,365-square-foot retail center on 36 acres at the southwest corner of Seventh Standard Road and Calloway Drive in northwest Bakersfield, Kern County, California. The Costco would cover about 184,478 square feet and include a fuel station. Halferty Development Company is the applicant. The City of Bakersfield issued a Notice of Preparation for an environmental impact report (EIR) on Aug. 19, 2026, and no hearing is scheduled. Disclosure: ASU Commercial, the brokerage of Kern CRE’s publisher, was a joint-venture developer and marketer of an earlier plan for this corner.

Key takeaways

  • The 7th Standard Marketplace would total about 225,365 square feet on 36 acres, including a Costco of about 184,478 square feet on a 20.8-acre parcel.
  • Bakersfield issued the notice on Aug. 19, 2026, and the State Clearinghouse comment window for SCH 2026080701 closes Sept. 21, 2026.
  • The notice schedules about 15 months of construction, from the fourth quarter of 2027 through the third quarter of 2028.
  • It would be Bakersfield’s third Costco, after the warehouses at 3800 Rosedale Highway and 4900 Panama Lane.
  • A regional brokerage report put Bakersfield retail vacancy at 5.2% in Q2 2026, with only 8,630 square feet under construction.

7th Standard Marketplace at a glance

ItemDetail
Project7th Standard Marketplace
LocationSouthwest corner of Seventh Standard Road and Calloway Drive, Bakersfield, CA 93314 (APN 492-060-12)
ApplicantJames Halferty, Halferty Development Company, LLC (applicant on the State Clearinghouse filing). The current landowner is not named in 2026 filings.
JurisdictionCity of Bakersfield (CEQA lead agency)
Case numbersPlanned Development Review No. 25-0022; Vesting Tentative Parcel Map No. 12633; SCH 2026080701
SizeAbout 36 acres split into 11 parcels; about 225,365 SF in nine single-story buildings plus a fuel facility; about 1,369 parking spaces
UseCostco warehouse (about 184,478 SF) with fuel, four drive-through restaurants, a drive-through bank, a car wash, retail and restaurant space
ZoningC-2/PCD (Regional Commercial/Planned Commercial Development); General Plan: General Commercial
StatusDraft EIR in preparation. Notice comment period closes Sept. 21, 2026. No hearing scheduled.
Next stepDraft EIR public review, then Planning Commission and City Council hearings (dates not set)

What is proposed at the 7th Standard Marketplace?

The plan subdivides a 36-acre agricultural parcel into 11 parcels and builds about 225,365 square feet of commercial space in nine single-story buildings, plus a fuel facility. The anchor is a Costco warehouse of about 184,478 square feet on roughly 20.8 acres.

The rest of the lineup is built for convenience trips: an automated car wash, four drive-through restaurants, a drive-through bank, a retail building and a retail/restaurant building. The fuel facility is a 128-square-foot kiosk under a canopy of about 11,655 square feet. A 2.39-acre drainage basin and about 1,369 parking spaces complete the site plan.

The city’s June 2026 request for proposals for an environmental consultant describes the north side of the site as about 40,800 square feet of retail, commercial and restaurant space in eight buildings, with the anchor store and fueling facility to the south. The Notice of Completion filing estimates 420 employees.

No rezoning is requested. The land is already zoned C-2/PCD with a General Commercial designation, so the approvals in play are Planned Development Review No. 25-0022 and Vesting Tentative Parcel Map No. 12633.

Where is the 7th Standard Marketplace Costco?

The site, APN 492-060-12, sits at the southwest corner of Seventh Standard Road and Calloway Drive in ZIP code 93314, on Bakersfield’s northern edge. The city’s RFP describes Seventh Standard Road to the north with single-family homes in Shafter beyond it, single-family homes to the south, Calloway Drive and vacant land to the east, and vacant land to the west.

The Notice of Completion lists State Route 99, Meadows Field, the Union Pacific main line and the Beardsley and Friant-Kern canals as nearby features. Norris Middle, Norris Elementary and Veterans Elementary are the nearby schools. The RFP notes one abandoned and plugged dry gas well near the site’s northeast corner and a PG&E major transmission line along Seventh Standard Road.

Earlier plans for the corner

This corner has been marketed for retail before. In November 2022, The Bakersfield Californian reported plans for a 20-acre shopping center at the southwest corner, expected to open in phases starting in early 2024 on land owned by the local Etcheverry family. ASU Commercial was the joint-venture developer with Pasadena-based Halferty Development Co. The 160,000-square-foot center was being pitched to restaurants, grocers and service providers.

An undated ASU Commercial marketing flyer showed 14 buildings totaling about 147,600 square feet on 20 acres, with anchor, shop and pad space available. That center was never built, and the city’s 2026 RFP still describes the site as vacant agricultural land. The current application expands the footprint to about 36 acres and puts a single warehouse-club anchor at its center.

Who is behind the 7th Standard Marketplace?

Halferty Development Company, LLC is the applicant on the State Clearinghouse filing, which lists James Halferty. The company’s website says James L. Halferty founded the firm in 1980 to develop mid-rise office buildings and neighborhood shopping centers held as long-term investments. His company bio cites more than 45 years in California real estate.

Halferty has built retail in Kern County before. Halferty Development Co. and Net Lease Alliance developed a Grocery Outlet-anchored center in Rosamond. In early 2022, four single-tenant buildings there (Grocery Outlet, Starbucks, 7-Eleven with fuel and O’Reilly Auto Parts, 28,462 square feet combined, built in 2021) sold for about $19.3 million, according to REBusinessOnline and The Registry. Bakersfield Now reported that the company also has projects at Stockdale Highway and Buena Vista Road and at Panama Lane and Old River Road. Halferty told the station, “Costco considers Bakersfield one of their primary locations. They do exceptionally well.”

Two details stand out. The city’s June 2026 RFP names Landmark Survey and Engineering, Inc. as the applicant, while the State Clearinghouse lists Halferty. Costco has not commented publicly on the project.

What does a new Costco mean for the Bakersfield retail market?

Bakersfield retail is tight, and very little is being built. A regional brokerage’s Q2 2026 Bakersfield retail report put vacancy at 5.2%, average NNN asking rent at $20.26 per square foot per year and 12-month net absorption at 344,991 square feet. NNN means the tenant pays taxes, insurance and maintenance on top of rent. Only 8,630 square feet was under construction in a 37.5-million-square-foot inventory.

The report credited part of that absorption to new Target stores. Two Targets of about 148,000 square feet each, on Gosford Road in Bakersfield and Woolomes Avenue in Delano, opened March 15, 2026, per Bakersfield Now. At about 225,365 square feet, the proposed center is more than 25 times the 8,630 square feet the report counted under construction market-wide.

National research points the same way. One national brokerage’s Q2 2026 U.S. retail report (July 29, 2026) showed availability unchanged at 4.9% and asking rents up 2.4% year over year to $24.79 per square foot, with historically low completions. Another national report for the quarter reported 4.4% vacancy and 10.2 million square feet of net absorption, led by freestanding stores and single-tenant boxes at nearly 7 million square feet. A third national report (July 15, 2026) put vacancy at 6.0%, with the development pipeline below 0.3% of inventory. A 2026 national retail outlook (Jan. 26, 2026) projected new retail construction to fall 37% in 2026 and noted that “Most current projects stem from tenant-driven demand, including expansions by large-format and warehouse retailers.” A Costco-anchored center fits that description.

Demand drivers and competition

The demand story is rooftops. In 2022, Ward 4 Councilman Bob Smith told The Bakersfield Californian, “It’s kind of the natural rhythm. You have to get the rooftops before the commercial follows.” The same article pointed to housing growth that includes Lennar’s Gossamer Grove on the north side of Seventh Standard in Shafter.

Bakersfield has two Costco warehouses today, at 3800 Rosedale Highway and 4900 Panama Lane, according to KGET. For owners of pads and shop space in northwest Bakersfield and Shafter, a third warehouse would add a strong traffic generator and new competition for drive-through, car wash, bank and fuel users. Another pending retail project is Riverview Marketplace.

The city’s RFP calls for peer review of an urban decay analysis, the CEQA study that tests whether a new large store could trigger closures that lead to physical blight. That chapter will be public when the Draft EIR is released. For how the process works, see our guide to the industrial land entitlement process and CEQA in Kern County.

Halferty’s Rosamond sale shows one exit path the company has used: build and lease single-tenant pads, then sell them individually to net-lease buyers. Pads beside a warehouse-club anchor tend to draw that kind of buyer.

What are the traffic concerns at 7th Standard and Calloway?

Traffic is the main concern raised so far. A resident identified as Maria told Bakersfield Now she was “for it, except for the traffic.” Neighbors told 23ABC that morning traffic already backs up near the site. One, Mike York, called the project “probably fifty-fifty” for him, citing worries about crime and theft as well as traffic. Other neighbors said the project would be a great addition and close enough to walk to.

According to 23ABC, the road plan includes:

  • The south half of Seventh Standard Road built to future six-lane expressway standards, with an auxiliary lane and a 30-foot landscaped parkway.
  • Calloway Drive built to arterial standards with a fully improved intersection at Seventh Standard Road. 23ABC described three lanes in each direction; Bakersfield Now described widening the two-lane road to four lanes.
  • Five access points: two right-in, right-out driveways on Seventh Standard Road and three on Calloway Drive with dedicated right-turn lanes.
  • A new traffic signal at the central Calloway Drive entrance, which would serve as the main entry.

Halferty told 23ABC, “The project will be conditioned by the City of Bakersfield to complete all required roadway improvements prior to the opening of Costco or any other businesses within the development.” Councilman Smith told Bakersfield Now he expects the project to pass environmental review and that the area’s roads can handle this type of development. Traffic study results have not been released. The RFP requires a traffic study with a vehicle miles traveled (VMT) analysis.

What happens next for the 7th Standard Marketplace?

The next public milestone is the Draft EIR, and the city has not announced a date. The Notice of Preparation opened scoping on Aug. 19, 2026, and the city scheduled a public scoping meeting for Aug. 31 at 1715 Chester Ave., according to KGET. The State Clearinghouse listing shows the comment window closing Sept. 21, 2026, and includes a comment letter from the Native American Heritage Commission.

The city’s RFP set a target of circulating the Draft EIR about six months after the consultant contract is awarded, with final consultant selection scheduled for Aug. 19, 2026. If that holds, a Draft EIR could appear in early 2027, but that is our estimate. Hearings before the Planning Commission and City Council would follow the Final EIR. The Bakersfield 2045 General Plan sets the broader land-use backdrop for northwest growth.

  • June 24, 2026: City posts an RFP for EIR consultant services and peer review of technical studies.
  • Aug. 19, 2026: Notice of Preparation issued (SCH 2026080701).
  • Aug. 31, 2026: Public scoping meeting scheduled at 1715 Chester Ave.
  • Sept. 21, 2026: Comment period closes.
  • Next: Draft EIR public review (date not set), then Planning Commission and City Council hearings.
  • Fourth quarter 2027 to third quarter 2028: Construction window in the notice, about 15 months.

Disclosure

ASU Commercial, the brokerage of Kern CRE’s publisher, is named above as a former joint-venture developer and marketer of this corner.

Frequently asked questions

Is Costco coming to northwest Bakersfield?

Costco is the proposed anchor of the 7th Standard Marketplace at Seventh Standard Road and Calloway Drive. The city’s August 2026 Notice of Preparation names a Costco warehouse of about 184,478 square feet with a fuel facility. The project still needs an environmental impact report and city approvals, and Costco has not commented publicly. It is proposed, not approved.

Where would the new Bakersfield Costco be located?

It would sit at the southwest corner of Seventh Standard Road and Calloway Drive in ZIP code 93314, on Assessor’s Parcel Number 492-060-12. The 36-acre site is farmland today. Homes in Shafter lie north of Seventh Standard Road, and single-family homes border the south side.

When would the 7th Standard Costco open?

No opening date has been announced. The notice estimates about 15 months of construction, from the fourth quarter of 2027 to the third quarter of 2028. The developer says the city will require roadway improvements before Costco or any other tenant opens. The project must first clear environmental review and city hearings.

Who is developing the 7th Standard Marketplace?

Halferty Development Company, LLC, a Pasadena-based firm founded in 1980, is the applicant on the State Clearinghouse filing. It was named in 2022 as joint-venture developer of an earlier 20-acre retail plan for the same corner, and it developed a Grocery Outlet-anchored center in Rosamond.

Does the 7th Standard Marketplace need a zone change?

No. The site is already zoned C-2/PCD, Regional Commercial with a Planned Commercial Development overlay. The requests are Planned Development Review No. 25-0022 and Vesting Tentative Parcel Map No. 12633, which would split the 36 acres into 11 parcels. The City of Bakersfield is preparing the EIR for those approvals.

How many Costco stores are in Bakersfield now?

Two: one at 3800 Rosedale Highway and one at 4900 Panama Lane, which Costco lists as its SW Bakersfield warehouse. The Seventh Standard Road store would be the city’s third. Halferty told Bakersfield Now that Costco considers Bakersfield one of its primary locations.

Can the public still comment on the 7th Standard Marketplace?

Yes, on the notice, until it closes Sept. 21, 2026. After that, the next chance comes when the city releases the Draft EIR for public review, followed by Planning Commission and City Council hearings. No dates are set. The city’s contact is the Development Services Department at 1715 Chester Ave., Bakersfield.

Own, lease or plan to buy retail near Seventh Standard Road? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us to talk through how the project could affect your property, pad pricing or leasing plans. Get Kern County CRE news monthly: subscribe to the Kern CRE report.

Sources

  1. 7th Standard Marketplace Project; Planned Development Review No. 25-0022 and Vesting Tentative Parcel Map No. 12633 (SCH 2026080701), CEQAnet / State Clearinghouse, received Aug. 20, 2026.
  2. 7th Standard Marketplace Notice of Preparation of a Draft EIR, City of Bakersfield via CEQAnet, Aug. 19, 2026.
  3. Notice of Completion and Environmental Document Transmittal, 7th Standard Marketplace, City of Bakersfield via CEQAnet, August 2026.
  4. Request for Proposal, Planned Development Review No. PDRN-25-0022, 7th Standard Marketplace Project, City of Bakersfield Development Services, hosted by Bakersfield Now, June 24, 2026.
  5. City doc outline 7th Standard Marketplace Project with “major anchor store”, Bakersfield Now, Aug. 19, 2026.
  6. Costco possibly coming to NW Bakersfield near 7th Standard Rd: docs, KGET, Aug. 19, 2026.
  7. Proposed Costco near Shafter-Bakersfield border sparks excitement, traffic concerns, Bakersfield Now, Aug. 21, 2026.
  8. Costco proposed near 7th Standard and Calloway in Bakersfield, 23ABC, Aug. 22, 2026.
  9. Commercial development to follow housing along 7th Standard, The Bakersfield Californian, November 2022.
  10. New Northwest Bakersfield Retail Development, SWC Seventh Standard Road & Calloway Drive (marketing flyer), ASU Commercial, undated.
  11. Company home page, Halferty Development Company.
  12. James L. Halferty, Halferty Development Company.
  13. $19.3M Sales of Four Single-Tenant Investments at Retail Center in Rosamond, California, REBusinessOnline, 2022.
  14. Halferty Development Sells 28,462 SQFT Retail Portfolio in Rosamond for $19.33MM, The Registry Southern California, Jan. 26, 2022.
  15. Regional brokerage market reports (Bakersfield retail, July 2026).
  16. Grand openings set March 15 for new Target stores on Gosford Road and in Delano, Bakersfield Now, Jan. 29, 2026.
  17. National brokerage market reports (U.S. retail, July 29, 2026).
  18. National brokerage market reports (U.S. retail, Q2 2026).
  19. National brokerage market reports (U.S. retail, July 15, 2026).
  20. Regional brokerage market reports (retail, Jan. 26, 2026).
  21. SW Bakersfield Warehouse (4900 Panama Ln), Costco Wholesale.

About this article

Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. ASU Commercial’s earlier role at this corner is disclosed above.

Featured image: a representative Costco warehouse, not the 7th Standard site. Photo by Jacob Blanck, Wikimedia Commons, CC BY-SA 4.0.

Get the Kern CRE Report

One email a month: the economic numbers that move commercial real estate, Kern County market statistics, and the deals and news shaping business here.

Free. Unsubscribe anytime.