Cadiz Northern Pipeline: Kern County Supervisors Back the 220-Mile Water Line Through East Kern

The Oct. 13 letter to the State Lands Commission is conditional on every approval and on pending lawsuits. A 1.1-mile segment on state land is the open question, with state action expected in early 2027.

Kern County supervisors voted 4-0 on Oct. 13, 2026, with one member absent, to send the State Lands Commission a letter supporting the Cadiz Northern Pipeline, a 220-mile former gas line that would carry Mojave Desert groundwater through East Kern. The support applies only if every required approval is completed and pending lawsuits are resolved.

Key takeaways

  • The Kern County Board of Supervisors approved the support letter 4-0 while Supervisor Leticia Perez was out of the room. No members of the public spoke.
  • County staff described the letter as conditional: support depends on all federal, state and local approvals and on the resolution of legal challenges.
  • The 30-inch buried steel line runs about 220 miles from Cadiz in San Bernardino County to Wheeler Ridge in Kern County. It enters Kern near Boron and follows Highway 58 west past Mojave and through the Tehachapi area.
  • Cadiz Inc. says the pipeline would deliver up to 25,000 acre-feet of water a year from its Mojave Groundwater Bank. County staff said they had not reviewed hydrology reports covering those figures.
  • The U.S. Bureau of Land Management approved a 50-year right-of-way in July 2026. Cadiz puts the cost to place the line in service at about $403.3 million.
  • About 1.1 miles of the line crosses state land. County staff said the State Lands Commission is expected to take up that segment in early 2027.

Cadiz Northern Pipeline letter at a glance

ItemDetail
ActionFull-board letter of support to the California State Lands Commission
Body and dateKern County Board of Supervisors, Oct. 13, 2026 (item 33)
Vote4-0, Supervisor Perez absent
ConditionAll federal, state and local approvals completed; legal challenges resolved
PipelineAbout 220 miles, 30-inch steel, Cadiz to Wheeler Ridge
Route in KernEnters near Boron, follows Highway 58, passes south of Mojave and through the Tehachapi and Cummings Valley areas, ends near Mettler
CapacityUp to 25,000 acre-feet a year (Cadiz)
Federal approvalBLM 50-year right-of-way, July 2026
Estimated costAbout $403.3 million to place in service (Cadiz, July 28, 2026)
Next state stepState Lands Commission action expected in early 2027

What did Kern County supervisors approve?

On Oct. 13, 2026, the Board of Supervisors approved a letter to the California State Lands Commission supporting the Cadiz Northern Pipeline. The item came from a Sept. 22 referral by the board’s Legislative Program Committee.

Thomas Brown of the County Administrative Office told the board the letter “expresses the county support for the project, provided that all required federal, state, and local regulatory processes are completed and any outstanding legal challenges are resolved.” The motion was to support the staff letter, and it passed with four ayes after the chair noted that Perez had stepped out.

The letter is a statement of support, not a permit. The county does not approve the pipeline.

What is the Cadiz Northern Pipeline?

The Cadiz Northern Pipeline is a former oil and gas line that Cadiz Inc. plans to convert to carry groundwater. County staff said it was built in the mid-to-late 1980s to move crude oil east from the Santa Barbara and Santa Maria basins and later passed to El Paso Natural Gas.

Cadiz bought a 96-mile segment from Cadiz to Barstow in 2014. It completed its purchase of the 124-mile Barstow-to-Wheeler Ridge segment after federal right-of-way grants in late 2020, according to the company’s December 2020 SEC filing. The filing describes a 30-inch buried steel pipeline.

Cadiz plans to move groundwater pumped from the Cadiz, Bristol and Fenner valley watersheds in the eastern Mojave Desert, which it calls the Mojave Groundwater Bank. The company says the line would serve High Desert and Inland Empire communities in San Bernardino County, according to Pipeline & Gas Journal. County staff said a July 2026 Cadiz release described a possible increase to 50,000 acre-feet a year after phase one.

The BLM approved a right-of-way in July 2026 to convert and operate the line across federal land for up to 50 years. Cadiz affiliate Fenner Gap Mutual Water Company has since signed guaranteed maximum price contracts with W.M. Lyles Co. for $218.9 million in pump stations and Mike Bubalo Construction for $54.9 million in pipeline work. The total estimated cost is $403.3 million, according to Construction Dive.

Where does the Cadiz Northern Pipeline run in Kern County?

The line enters Kern County near Boron and parallels Highway 58, county staff told the board. It continues west to just south of Mojave, passes through the Tehachapi and Cummings Valley areas and drops into the San Joaquin Valley, ending near Mettler. Cadiz’s 2020 filing gives the western end as Wheeler Ridge.

The route shares an East Kern corridor with the Mojave Micro Mill site between Mojave and Rosamond, several solar and battery projects and Tehachapi’s farm and residential valleys.

What approvals and lawsuits are still pending?

Three items remain open: the State Lands Commission, state findings under SB 307 and federal litigation.

State Lands Commission. County staff said about 1.1 miles of the pipeline crosses state land. When El Paso sold the line, it did not obtain the commission’s consent to assign its state lease to Cadiz. In December 2024 the commission ended that lease, gave El Paso a temporary caretaker lease and ordered a decommissioning plan. El Paso filed a plan in December 2025 to cap the segment and fill it with concrete slurry. Cadiz separately asked the commission in March 2026 to review the line’s use for water.

Staff said commission action on both is expected in early 2027, and that approval of the decommissioning plan “could potentially affect the viability” of using the pipeline for water.

SB 307. A 2019 state law requires the commission, consulting with state resource agencies, to make certain findings before desert groundwater can move through public conveyance facilities, county staff said.

Groundwater rules. The source basins are rated very low priority under the Sustainable Groundwater Management Act, so San Bernardino County’s desert groundwater ordinance governs them. Staff said the county’s agreement with the project lets it monitor groundwater and reduce or stop pumping if harm occurs. The agreement also reserves 25,000 acre-feet of groundwater for county use and sets aside 20% of annual yield for possible county use over 50 years.

Lawsuits. Several environmental organizations and the Fort Mojave and Chemehuevi Indian tribes have sued over the BLM’s July approval, county staff said. The plaintiffs cite potential harm to desert groundwater, springs and seeps, wildlife habitat and cultural resources, according to Jurist.

Could Kern County get water from the Cadiz Northern Pipeline?

Not under any announced contract. Supervisor Jeff Flores said the letter was about “the long-term water interests of Kern County.” Because the line ends in Kern, he said, water not used in San Bernardino County could potentially help local groundwater, agriculture and disadvantaged communities.

A community consultant for Cadiz told the board that Boron, Rosamond, the City of Tehachapi, North Edwards and the Arvin Community Services District had sent support letters. The consultant said any water left over for Kern would go to disadvantaged communities.

No Kern buyer or delivery contract was named at the meeting, and Cadiz’s announced customers are in San Bernardino County. Any Kern supply would depend on surplus water, state approvals, the lawsuits and new agreements.

What else did Kern supervisors approve on Oct. 13?

The session’s consent calendar included several other land items. As of Oct. 23, 2026, the county had not posted minutes.

  • County leases: An amendment to the Fire Department lease at 34920 Petrol Road in Bakersfield corrects the landlord’s name to North Meadows Business Park Properties LLC. An amendment to the Department of Human Services lease at 100 E. California Ave. extends its early termination date and sets maintenance duties.
  • Farmland contracts: A Williamson Act contract with Primex Farms LLC covers 121.73 acres. A Farmland Security Zone contract with the Ali and Mojgan Amin trust covers 268.89 acres. Both are in Agricultural Preserve No. 6.
  • Other items: A utility easement to Oildale Mutual Water Company, County Service Area 71 zones for Tract 7162 near Jenkins and Hageman roads, up to $1.25 million from the Road Fund for a Patton Way building rehabilitation and, at the 9 a.m. session, a $184,783 emergency boiler replacement at the California Aeronautical University building at Meadows Field.

The 2 p.m. consent calendar also covered a street vacation for the Housing Authority’s Rio Vista site in Oildale. For other decisions that week, see Kern CRE’s Oct. 12-23 development approvals roundup.

What does the Cadiz Northern Pipeline mean for East Kern land and development?

Water is the first question for any large East Kern project, from manufacturing to industrial and energy sites. A new imported supply, even a small one, would matter to towns along Highway 58 that rely on groundwater and State Water Project deliveries. The letter adds no water today, and the pipeline’s main customers are outside Kern.

For owners along the route, the line already sits in an existing corridor. Land the pipeline crosses can expect conversion work and pump station construction as the project moves ahead.

Investors can compare the project with other long-running water disputes, such as the Kern River flow lawsuit: a possible upside that depends on courts and state agencies, not a supply to underwrite today. Water and utility capacity also shape industrial land entitlements in Kern County and the broader logistics corridors along I-5, SR-99 and SR-58. The State Lands Commission’s early 2027 decisions are the next milestone.

Frequently asked questions

What is the Cadiz Northern Pipeline?

It is a roughly 220-mile, 30-inch former oil and gas pipeline that Cadiz Inc. plans to convert to carry groundwater from eastern San Bernardino County. The line runs from Cadiz to Wheeler Ridge in Kern County.

Did Kern County approve the Cadiz pipeline?

No. The Board of Supervisors voted 4-0 on Oct. 13, 2026 to send a support letter to the State Lands Commission. The support is conditional on all approvals and on lawsuits being resolved, and the county issues none of the pipeline’s permits.

Where does the pipeline run in Kern County?

County staff said it enters Kern near Boron and parallels Highway 58. It passes just south of Mojave and through the Tehachapi and Cummings Valley areas before ending near Mettler in the southern San Joaquin Valley.

How much water would the Cadiz Northern Pipeline carry?

Cadiz says the line would start at up to 25,000 acre-feet a year, with a possible increase to 50,000 acre-feet after phase one. County staff said they had not reviewed hydrology reports covering those figures.

What approvals does the pipeline still need?

The State Lands Commission must act on the 1.1-mile segment that crosses state land and make the findings SB 307 requires. County staff expect that action in early 2027. Lawsuits over the BLM’s July 2026 right-of-way are also pending.

Will Kern County get water from the pipeline?

No Kern contract has been announced. Flores said surplus water could help Kern because the line ends in the county, but Cadiz’s announced customers are in San Bernardino County.

Buying, leasing or developing land in East Kern and need to know how water and infrastructure affect a site? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us. Get Kern County CRE news monthly: subscribe to the Kern CRE report.

Sources

  1. Regular meeting, Oct. 13, 2026, 2 p.m. session (video), Kern County Board of Supervisors, Oct. 13, 2026.
  2. BLM grants right-of-way permits for the Northern Pipeline (Form 8-K), Cadiz Inc., U.S. Securities and Exchange Commission, Dec. 23, 2020.
  3. BLM Approves 220-Mile Gas-to-Water Pipeline Conversion in California, Pipeline & Gas Journal, July 10, 2026.
  4. Cadiz contracts 2 builders for $403M Southern California water pipeline, Construction Dive, Aug. 4, 2026.
  5. Environmentalists and tribes sue Bureau of Land Management over approval of Mojave Desert pipeline, Jurist, July 2026.

About this article

Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.

Get the Kern CRE Report

One email a month: the economic numbers that move commercial real estate, Kern County market statistics, and the deals and news shaping business here.

Free. Unsubscribe anytime.