The plan would rezone mostly industrial land in northwest Bakersfield for a water park, retail, medical offices, hotels and smaller industrial lots. Here is what is proposed, what the Draft EIR found and how to comment by Dec. 7.
The City of Bakersfield opened public review of the Tortuga Bay Water Park Draft Environmental Impact Report on Oct. 23, 2026. The plan would rezone about 152 mostly industrial acres at Hageman Road and Mohawk Street in northwest Bakersfield, California, for a 26.5-acre water park, retail, medical offices, two hotels and smaller industrial lots. Comments are due Dec. 7.
Key takeaways
- Bakersfield’s 45-day public review of the Tortuga Bay Water Park Draft EIR runs from Oct. 23 to 5 p.m. Dec. 7, 2026.
- The 152-acre site at the southeast corner of Hageman Road and Mohawk Street is planned and zoned for light, service and heavy industry today. General Plan Amendment/Zone Change No. 24-0377 would shift most of it to commercial, park and recreation use.
- The Draft EIR describes a 26.5-acre water park, a 4.4-acre golf range, about 360,000 square feet of general commercial space, medical offices with a 150-bed surgery center, two 120-room hotels and light and service industrial lots, built in three phases through 2042.
- One impact could not be mitigated: vehicle miles traveled from the retail component. Approving the project as proposed would require a statement of overriding considerations.
- The Draft EIR estimates 3,000 to 4,000 jobs, counting construction, seasonal and full-time positions.
Tortuga Bay Water Park at a glance
| Item | Detail |
|---|---|
| Project | Tortuga Bay Water Park Project |
| Owner and applicant | Tortuga Bay Water Park, LLC |
| Lead agency | City of Bakersfield, Development Services Department, Planning Division |
| Location | Southeast corner of Hageman Road and Mohawk Street, northwest Bakersfield |
| Size | About 152 gross acres (152.69 acres on the state filing) |
| Current land use | Vacant; Light, Service and Heavy Industrial designations with M-1, M-2 and M-3 zoning |
| Requested approvals | General Plan Amendment/Zone Change No. 24-0377, plus a parcel map, site plan review and conditional use permit |
| Environmental review | Draft EIR, SCH No. 2026020370; public review Oct. 23 to Dec. 7, 2026 |
| Jobs | About 3,000 to 4,000, counting construction, seasonal and full-time positions (Draft EIR) |
| Next step | Comments due 5 p.m. Dec. 7, 2026; then a Final EIR, a Planning Commission hearing and a City Council decision |
What is proposed at the Tortuga Bay Water Park site?
Tortuga Bay Water Park, LLC, the property owner and applicant, wants new land use designations and zoning so it can build a mix of recreation, commercial and industrial uses on vacant land. The Draft EIR describes this program:
- A water park of about 26.5 acres with a wave pool, a lazy river, three slide towers, children’s and spray areas and 322 parking spaces.
- A 4.4-acre golf range.
- About 360,000 square feet of general commercial space, including a retail village, restaurants and a gas station.
- Medical offices and a 150-bed surgery center.
- Two 120-room hotels.
- Light and service industrial lots for uses such as contractor yards, equipment rental, truck repair, metal fabrication, warehouses and light manufacturing.
How big would the water park be?
The tallest attraction would stand 60 feet, and most commercial and industrial buildings would be 20 to 35 feet tall. The park would open seasonally, April through November, from 10 a.m. to 8 p.m. The Draft EIR estimates 1,900 to 2,100 guests on a typical day. Parking would be paid and gated, and the park could host private events on 10 to 15 days a year. About 6 acres inside the park would be held for more slides later.
How would Tortuga Bay be phased?
The Draft EIR splits construction into three phases, with full buildout by 2042 (the state filing lists 2040). The breakdown below comes from the Draft EIR’s Table 3-2. The city’s Notice of Availability gives a later start for phases II and III, 2030 and 2035, so the dates are planning estimates.
| Phase | Components |
|---|---|
| Phase I (2027 to 2032) | Water park (26.5 acres), golf range (4.4 acres), 235,000 SF of general commercial on 18.61 acres, 6.35 acres of light industrial and 9.95 acres of service industrial |
| Phase II (2032 to 2037) | Medical offices (37,000 SF on 5.31 acres), 90,000 SF of general commercial on 6.39 acres, 6.17 acres of light industrial and 10.52 acres of service industrial |
| Phase III (2037 to 2042) | Surgery center (150 beds on 3.12 acres), two 120-room hotels (4.75 acres), 35,000 SF of general commercial on 2.86 acres, 3.23 acres of light industrial and 9.39 acres of service industrial |
Where is the Tortuga Bay site?
The vacant site sits at the southeast corner of Hageman Road and Mohawk Street in northwest Bakersfield. According to the Draft EIR, homes line Mohawk Street to the west. Hageman Road, more homes and two residential care facilities sit to the north. Knudsen/Landco Drive and a railroad right-of-way border the east side, and the Beardsley Canal Ditch, the Calloway Canal and heavy industrial land lie to the south.
The land lies within the Fruitvale Oil and Gas Field and holds about 15 plugged and abandoned oil and gas wells. Most of it falls in Compatibility Zone C of the airport land use plan for Meadows Field, the Draft EIR says. The project would finish the western part of Landco Drive along the east edge and extend Krebs Road east to west through the site.
What would change for the site’s industrial zoning?
Today the whole site is planned and zoned for industry, with Light, Service and Heavy Industrial designations and M-1, M-2 and M-3 zoning. General Plan Amendment/Zone Change No. 24-0377 would move most of it to General Commercial and to park and recreation use, keeping a smaller amount of industrial land on the southern part of the site. The Draft EIR describes the plan as “downgrading the existing entitled medium and heavy industrial designations” on the north, west and south sides, where the site meets homes.
The state filing counts 45.61 acres of industrial development in the plan, about 30% of the site. The rest of the land, more than 100 acres, would leave the industrial supply. For how industrial land is zoned across the area, see our guide to industrial zoning in Bakersfield and Kern County.
Industrial projects nearby
The Draft EIR’s list of nearby projects includes a separate request by Hageman Properties, LLC to change about 78.94 acres at the southeast corner of Hageman Road and Landco Drive from Heavy Industrial to Service Industrial (General Plan Amendment/Zone Change No. 22-0263). That site could hold up to 1,197,643 square feet of buildings, 40% manufacturing and 60% warehouse, the Draft EIR says.
Elsewhere in northwest Bakersfield, about 1,650 acres of orchards are being marketed as an industrial megasite; see our report on Rosedale Ranch.
What did the Tortuga Bay Draft EIR find?
With mitigation, the Draft EIR finds that every impact can be reduced below the level of significance except one: vehicle miles traveled from the general commercial retail component, at both the project and cumulative levels. If the city approves the project as proposed, it would have to adopt a statement of overriding considerations explaining why the benefits outweigh that impact. The proposed fix is a transportation demand management plan for the retail area, drawing on options such as transit passes and carpool incentives for retail workers, electric vehicle charging and bicycle facilities, with five years of monitoring.
The Draft EIR studied three alternatives. A Reduced Retail Alternative would cut general commercial space from about 360,000 square feet to less than 50,000 square feet of local-serving retail, avoiding the traffic finding but producing less sales tax revenue and fewer jobs. A Water Park Only Alternative would build just the park and leave the rest of the site under its current industrial designations. The Draft EIR names the Water Park Only Alternative as the environmentally superior choice among the build options.
What concerns came up?
Comments on the Notice of Preparation raised noise, lighting, traffic, parking, security, drainage, water pressure and sewer capacity from nearby residents, according to the Draft EIR. The California Department of Fish and Wildlife asked about special-status species such as the San Joaquin kit fox and Swainson’s hawk. The California Department of Justice raised warehousing near sensitive receptors, and the North Kern Water Storage District asked for a 6-foot block wall along the Calloway Canal. The Water Supply Assessment estimates demand of about 280 acre-feet a year at full buildout, including about 96 acre-feet for the water park.
Who is behind Tortuga Bay, and how did it get here?
Local businessman Mike Ross has pursued a Bakersfield water park for years. He told The Bakersfield Californian in November 2025 that he had looked at 25 to 30 possible locations and chose this one after meeting with city officials and engineers. His previous Tortuga Bay proposal, in 2017, targeted Hart Park and fell through, the newspaper reported.
The city filed a Notice of Preparation for this environmental review in February 2026 and filed the Draft EIR with the State Clearinghouse on Oct. 22, 2026.
How can you comment on the Tortuga Bay Draft EIR?
Written comments on the project or the Draft EIR are due by 5 p.m. Monday, Dec. 7, 2026. Send them to Louis Ramirez, Associate Planner, City of Bakersfield Development Services Department, Planning Division, 1715 Chester Ave., 2nd Floor, Bakersfield, CA 93301, or by email to LRamirez@bakersfieldcity.us. The Draft EIR and its appendices are posted on the city’s environmental documents page and on CEQAnet.
After the comment period, the city will publish written responses at least 10 days before a Planning Commission hearing. The commission will consider the Final EIR and can recommend it to the City Council, which decides on certification and on the general plan amendment and zone change. No hearing date has been set.
What does Tortuga Bay mean for commercial real estate?
It would take more than 100 acres of industrial land out of a part of town where industrial users already cluster near Meadows Field and State Route 99. A national brokerage’s Bakersfield industrial report put availability at 10.1% in Q2 2026, with about 6.8 million square feet available in a 67.4 million-square-foot inventory and about 13.1 million square feet in the proposed pipeline. Approved campuses such as the Airport Commerce Center keep adding north-side options.
It would also add a large retail and hospitality node. A regional brokerage’s Q2 2026 Bakersfield retail report put vacancy at 5.2%, with just 8,630 square feet under construction in a 37.5 million-square-foot market. About 360,000 square feet of new commercial space would be a large addition to that pipeline, and the retail piece carries both the project’s sales tax case and its one unavoidable impact.
Our read: with that much proposed industrial space marketwide, losing this site is unlikely to tighten the market by itself, and land wedged against homes is where industrial projects draw the most opposition. The Reduced Retail Alternative is the one to follow. If the city leans that way, the commercial space shrinks to under 50,000 square feet, which matters for anyone pricing nearby retail or industrial land. The city is also rewriting its land use map; see our look at the draft 2045 General Plan.
Frequently asked questions
What is the Tortuga Bay Water Park project?
It is a proposed mixed-use development on about 152 acres in northwest Bakersfield. The Draft EIR describes a 26.5-acre water park, a 4.4-acre golf range, about 360,000 square feet of general commercial space, medical offices and a surgery center, two 120-room hotels and light and service industrial lots.
Where would the Tortuga Bay Water Park be built?
At the southeast corner of Hageman Road and Mohawk Street in northwest Bakersfield, Kern County, California. The vacant site is planned and zoned for industrial use today and borders homes to the north and west and industrial land to the east and south.
When are comments on the Tortuga Bay Draft EIR due?
Written comments are due by 5 p.m. Dec. 7, 2026. The city’s planner for the project, Louis Ramirez, takes them at 1715 Chester Ave., 2nd Floor, Bakersfield, CA 93301, or LRamirez@bakersfieldcity.us.
Has Bakersfield approved the Tortuga Bay Water Park?
No. The project is in public review of its Draft EIR. After the comment period, the city will prepare a Final EIR for a Planning Commission hearing, and the City Council makes the final decision on the general plan amendment and zone change. No hearing date has been set.
When would the Tortuga Bay Water Park open?
No opening date has been announced. The Draft EIR puts the water park in the first phase, scheduled for 2027 to 2032. Those dates are planning assumptions and depend on approval and financing.
What did the Tortuga Bay Draft EIR find?
It found that all impacts can be reduced below significance with mitigation except vehicle miles traveled from the retail component. It also studied a reduced retail version and a water park only version, either of which would avoid that impact.
How many jobs would the Tortuga Bay project create?
The Draft EIR estimates about 3,000 to 4,000 jobs, counting construction, seasonal and full-time positions. The state filing lists 3,500. The final number depends on which businesses lease the commercial, medical and industrial space.
Own industrial or retail property in northwest Bakersfield, or weighing land near Hageman Road? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us. Get Kern County CRE news monthly: subscribe to the Kern CRE report.
Sources
- Tortuga Bay Water Park Project, Draft EIR filing (SCH 2026020370), CEQAnet (State Clearinghouse), received Oct. 22, 2026.
- Tortuga Bay Water Park Project, Draft Environmental Impact Report, City of Bakersfield, October 2026.
- Notice of Availability of a Draft Environmental Impact Report, Tortuga Bay Water Park Project; General Plan Amendment/Zone Change No. 24-0377, City of Bakersfield, Oct. 21, 2026.
- Tortuga Bay Water Park Project, Notice of Preparation, CEQAnet (State Clearinghouse), received Feb. 10, 2026.
- Environmental Documents, City of Bakersfield, accessed Oct. 23, 2026.
- Same plan, different location for proposed Tortuga Bay Water Park, The Bakersfield Californian, Nov. 17, 2025.
- Bakersfield industrial market report, Q2 2026, national brokerage research, Q2 2026.
- Q2 2026 Bakersfield, CA Retail Market Overview, regional brokerage research, July 2026.
About this article
Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.