Mojave Micro Mill: Kern County’s $3.375 Million Incentive for 450 Steel Jobs

Pacific Steel Group’s rebar mill, approved in 2024 and under construction since 2025, came back to the Board of Supervisors for a job-creation deal.

The Mojave Micro Mill is Pacific Steel Group’s rebar mill under construction on 174 acres at Sierra Highway and Sopp Road, between Mojave and Rosamond in unincorporated Kern County, California. The Kern County Board of Supervisors approved its permits and environmental report on March 19, 2024. The board’s Sept. 29, 2026, agenda recommended a retroactive Advance Kern incentive of up to $3,375,000 for 450 new jobs. Published minutes had not confirmed the vote.

Key takeaways

  • The Sept. 29, 2026, Board of Supervisors agenda carried a retroactive Advance Kern agreement with Pacific Steel Group, PSGM3 LLC. It covers 450 new full-time, living-wage jobs and is capped at $3,375,000 from the General Fund.
  • Supervisors certified the mill’s environmental impact report (EIR) and approved its rezoning from A-1 agriculture to M-3 PD heavy industrial on March 19, 2024.
  • The project combines a 489,200-square-foot mill, 61,721 square feet of accessory buildings and a 63-acre solar array on 174 acres.
  • Construction began March 5, 2025. Pacific Steel said in March 2026 that it expects to start ramping up by July 2027 and reach full capacity in early 2028.
  • A national brokerage report put Bakersfield industrial availability at 10.1% in Q2 2026, with one project of about 510,000 square feet under construction.

Mojave Micro Mill at a glance

ItemDetail
ProjectMojave Micro Mill (rebar micro mill) and Advance Kern economic development incentive agreement
LocationSoutheast corner of Sierra Highway and Sopp Road, unincorporated southeastern Kern County, about 5 miles northeast of Rosamond and 8 miles southeast of Mojave (APNs 431-010-02 and 431-030-02)
Applicant/ownerPacific Steel Group (San Diego); PSGM3 Holdings Corp (CEQA applicant) and PSGM3 LLC (incentive and California Energy Commission grant)
JurisdictionKern County Board of Supervisors (Supervisorial District 2)
Case numbersPP22402; GPA 3, ZCC 62, CUP 71, CUP 72, PD Plan 3, ZV 24, ZV 25 (all Map 213); SCH 2022100646
Size174 acres; 489,200 SF mill plus 61,721 SF accessory buildings (550,921 SF total); 63-acre solar array
UseScrap-fed electric arc furnace mill producing rebar; projected 380,000 to 450,000 tons a year
IncentiveUp to $3,375,000 for 450 new full-time living-wage jobs, commencing June 29, 2026 (General Fund; not budgeted)
StatusPermits approved March 19, 2024; under construction since March 5, 2025; incentive on the Sept. 29, 2026, agenda with approval recommended, vote not confirmed
Next stepBoard minutes confirming the incentive vote; company targets ramp-up by July 2027 and full capacity in early 2028

What did Kern County consider for the Mojave Micro Mill?

Kern County’s supervisors had a $3,375,000 job-creation incentive for Pacific Steel Group on their Sept. 29, 2026, agenda. Staff recommended approval. The board agenda listed Item 28 in the afternoon session as a “proposed retroactive Advance Kern Economic Development Incentive Agreement with Pacific Steel Group, PSGM3 LLC.” It covers 450 new, full-time, permanent living-wage jobs, starts June 29, 2026, and asks the chairman to sign.

The agenda lists the fiscal impact as $3,375,000 from the General Fund, not budgeted and discretionary. By our calculation, the cap works out to $7,500 per job. That figure is ours, not the county’s. Published minutes confirming the board’s action were not available.

The agenda does not name a site. PSGM3 is the name Pacific Steel uses for its Mojave project in state records, however. The California Energy Commission’s $14 million storage grant went to PSGM3, LLC to serve “PSG’s planned zero process emission steel mill near Mojave.” The mill’s CEQA applicant was PSGM3 Holdings Corp.

How does the Advance Kern program work?

Advance Kern is the county’s business attraction program. Supervisors approved it in November 2017, according to a Tejon Ranch Co. release. The program site describes performance-based rebates of property, sales, use and transient occupancy taxes, reviewed case by case, with a preference for jobs that pay better than a living wage.

The agenda listing did not include the payment schedule or job-verification terms of the Pacific Steel agreement.

What state support is already in place?

The county deal adds to state commitments. The Governor’s Office of Business and Economic Development’s California Competes committee unanimously approved a $30 million tax credit on April 25, 2024, tied to 447 new full-time jobs and $542 million in investment. The Energy Commission grant, agreement LDS-24-002, funds a 32 MWh non-lithium-ion long-duration storage system. It was approved Jan. 21, 2025.

Where is the Mojave Micro Mill?

The mill occupies two parcels totaling 174 acres at the southeast corner of Sierra Highway and Sopp Road in unincorporated southeastern Kern County. The county’s notice of availability places it about 5 miles northeast of Rosamond and 8 miles southeast of Mojave.

The 2022 Initial Study puts the site about 1.25 miles southeast of the State Route 14 and Backus Road exit. The Union Pacific Railroad and Sierra Highway run along its west side, and Edwards Air Force Base borders it on the east. Shemshad Food Products and Desert Block Co. sit to the north.

What was on the site before the mill?

The land was close to raw. The Initial Study says the northwest corner was once farmed seasonally and “had historically been used for unpermitted storage by the previous property owner.” The balance was undeveloped. The site carried a Map Code 8.5 (Resource Management) general plan designation and A-1 (Limited Agriculture) zoning.

The approvals changed the designation to 7.3 (Heavy Industrial) and the zoning to M-3 PD (Heavy Industrial, Precise Development Combining). The case set is PP22402, covering a general plan amendment, zone change, two conditional use permits, a precise development plan and two zone variances, all on Map 213. The 2022 notice of preparation said one variance would cut required parking from 993 to 246 spaces.

Entitlement and CEQA timeline (SCH 2022100646)

  • April 5, 2022: Pacific Steel selects Danieli for a MIDA Hybrid micro mill, then pegged at about $350 million and 380,000 tons of nominal annual capacity.
  • Oct. 28, 2022: Kern County issues the notice of preparation for a 475,800-square-foot mill.
  • Nov. 17, 2023: The draft EIR is released with a 489,200-square-foot mill and 61,721 square feet of accessory buildings. Comments closed Jan. 2, 2024.
  • Feb. 8, 2024: The Planning Commission recommends approval 4-0. One commissioner recuses himself over a potential conflict of interest.
  • March 19, 2024: The Board of Supervisors certifies the EIR and approves the project and adopts a statement of overriding considerations.
  • Jan. 31, 2025: The California Department of Fish and Wildlife issues a Joshua tree incidental take permit covering 198 trees. An amendment on March 18, 2025, raised the total to 204.
  • March 5, 2025: Groundbreaking.
  • Sept. 29, 2026: The Advance Kern incentive goes to the board with a recommendation to approve.

Who is behind the Mojave Micro Mill?

Pacific Steel Group is a San Diego reinforcing steel fabricator and installer founded in 2014, according to its website and 2020 trade coverage. Eric Benson is chairman and CEO. Mark Olson, vice president of mill operations, represented the company at the 2024 Planning Commission and board hearings.

The mill is a vertical integration play. Pacific Steel has bought rebar to fabricate and install, and the mill lets it make its own from scrap. At the groundbreaking, Benson called it “the first tangible step toward full vertical integration of our reinforcing steel operations,” per the company’s release.

Getting here took a fight. In 2020 the company sued Commercial Metals Co. (CMC), alleging an exclusivity deal with Danieli kept rival mills out of a 500-mile radius around CMC’s Rancho Cucamonga mill, Fastmarkets reported. A federal jury found CMC liable on Nov. 5, 2024, and awarded $110 million, which CMC said trebles to $330 million. After the court denied CMC’s post-trial motions in September 2025, CMC said it would appeal to the Ninth Circuit.

Danieli is now the main contractor, with Hatch Engineering handling site management and procurement, Construction Equipment Guide reported in July 2025. The stated investment has grown from about $350 million in 2022 to $540 million at approval and more than $600 million at groundbreaking. A 2025 CEQA filing cites $630 million.

What does the Mojave Micro Mill mean for Kern County industrial real estate?

The mill is an owner-user heavy industrial plant, not speculative space, so it adds no leasable inventory. Its market effect is more likely to show up indirectly, through payroll, suppliers, trucking and service firms that need yards and small shop buildings along the State Route 14 corridor. For owners of small-bay and yard properties in East Kern, that is the demand to watch. Our guide to reading an industrial market report explains the vacancy and absorption terms below.

No major brokerage publishes statistics for Mojave or Rosamond, so the closest benchmarks are Bakersfield metro reports. A national brokerage’s Q2 2026 Bakersfield industrial report put availability at 10.1%, up 20 basis points from a year earlier, with about 6.8 million square feet available. Asking rent averaged $0.71 per square foot per month, triple net. Only one project, a 510,000-square-foot building in Arvin, was under construction, against 13.1 million square feet proposed.

A regional brokerage’s Q2 2026 Bakersfield industrial report measured vacancy at 9.55%, down from 10.90% in Q1 2026. It reported 1,489,196 square feet of net absorption over 12 months and a 7.23% cap rate. The report noted that logistics buildings face more vacancy and pricing pressure while “specialized and flex properties maintain stronger occupancy and rental rates.”

Nationally, a Q2 2026 U.S. industrial and logistics market report said manufacturers accounted for more than 12% of leasing volume and pointed to infrastructure projects and defense spending as drivers of future manufacturing demand. A rebar mill aimed at California construction fits that pattern.

Demand drivers to watch in East Kern

  • Jobs: The EIR planned for about 440 employees, and the county agreement covers 450. A national brokerage report put Bakersfield metro unemployment at 8.5% in Q2 2026.
  • Trucks: The 2022 Initial Study projected 97 inbound trucks a day carrying raw materials and supplies and 74 outbound product deliveries a day.
  • Scrap supply: Olson told Recycling International the mill will source scrap within a 300 to 400 km radius, citing “an abundance of scrap and recyclers in the greater Los Angeles area.”
  • Power and water: The 2022 Initial Study listed the 63-acre solar array at 10 MW and water supply of roughly 1,018 acre-feet a year from the Antelope Valley-East Kern Water Agency. The state grant adds a 32 MWh storage system.

Other East Kern energy and industrial projects are moving through review as well, including the RB Inyokern Data Center, the Euismod energy storage project near Rosamond and the Airport Commerce Center near Meadows Field.

What concerns and conditions came with the Mojave Micro Mill approval?

The EIR found significant and unavoidable impacts to air quality and noise at the project level, plus cumulative impacts to aesthetics, biological resources and wildfire. Supervisors adopted a statement of overriding considerations.

Approval came with 61 mitigation measures. They include a $100,000 annual payment to the fire department for carbon dioxide response training, infrared leak detection cameras and on-site Joshua tree relocation, the Mojave Desert News reported. No members of the public spoke at the Planning Commission hearing. At the board, Emma De La Rosa of Leadership Counsel for Justice and Accountability questioned the carbon capture technology, and Robert Colson raised groundwater contamination risks.

Support was broad. Then-2nd District Supervisor Zack Scrivner backed the project, and a Carpenters union local supported it, the Desert News reported. Kern Economic Development Corp. President Richard Chapman called it “a home run,” per Tehachapi News. The board vote was unanimous.

What happens next for the Mojave Micro Mill?

The next milestone is the board’s recorded action on the incentive, followed by hiring and a start-up targeted for mid-2027.

  • Incentive vote: Published minutes had not recorded the board’s final action.
  • Hiring: In March 2026, Pacific Steel’s Carly Sullivan told the Mojave Chamber the company was onboarding its first five hourly maintenance workers “out of the 400 that we’re planning to hire.” About 100 hires were expected in 2026.
  • Start-up: Olson told Recycling International in March 2026, “We will begin our ramp-up period by July 2027 and expect to be at full capacity in early 2028.”
  • Litigation: CMC said in September 2025 that it would appeal the $330 million antitrust judgment to the Ninth Circuit.

Frequently asked questions

What is the Mojave Micro Mill?

It is a steel mill being built by San Diego-based Pacific Steel Group to turn scrap metal into rebar in an electric arc furnace. The plant includes a 489,200-square-foot mill, 61,721 square feet of accessory buildings and a 63-acre solar array on 174 acres of unincorporated Kern County. The company projects 380,000 to 450,000 tons of rebar a year.

Where is the Mojave Micro Mill located?

The mill sits at the southeast corner of Sierra Highway and Sopp Road, about 5 miles northeast of Rosamond and 8 miles southeast of Mojave. The State Route 14 and Backus Road exit is roughly 1.25 miles away. Union Pacific tracks run to the west and Edwards Air Force Base lies to the east. The parcels are APNs 431-010-02 and 431-030-02.

How many jobs will the Mojave Micro Mill create?

Official commitments cluster at 440 to 450 permanent jobs. The EIR assumed roughly 440 employees, the state tax credit is tied to 447 new full-time jobs, and the Advance Kern agreement covers 450. Pacific Steel’s website cites a broader figure of nearly 1,000 jobs in Kern County. The company said in March 2026 that it expected about 100 hires this year.

What incentive did Kern County consider for Pacific Steel Group?

Supervisors had a retroactive Advance Kern incentive agreement with Pacific Steel Group, PSGM3 LLC, on their Sept. 29, 2026, agenda. It pays up to $3,375,000 from the General Fund for 450 full-time living-wage jobs counted from June 29, 2026. Staff recommended approval, but published minutes had not confirmed the vote.

When will the Mojave Micro Mill open?

Construction began March 5, 2025. Pacific Steel’s vice president of mill operations said in March 2026 that ramp-up should begin by July 2027, with full capacity in early 2028. Earlier company statements pointed to commissioning in the first quarter of 2027, so the schedule has slipped modestly.

Did the Mojave Micro Mill go through CEQA review?

Yes. Kern County prepared a full EIR under State Clearinghouse number 2022100646. The Planning Commission voted 4-0 on Feb. 8, 2024, to recommend approval, and supervisors certified the EIR on March 19, 2024. They adopted a statement of overriding considerations for air quality, noise and other impacts. The state wildlife department later issued a Joshua tree take permit.

Why is it called California’s first steel mill in 50 years?

Pacific Steel and the Governor’s office describe it as the first steel mill built in California in more than 50 years. Olson told supervisors in 2024 that no steel was being made in the state. CMC’s former Rancho Cucamonga mill, at the center of Pacific Steel’s antitrust case, no longer operates, according to Fastmarkets.

Questions about how the Mojave Micro Mill could affect industrial land, leasing or values in East Kern and along the State Route 14 corridor? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us. Get Kern County CRE news monthly: subscribe to the Kern CRE report.

Sources

  1. Board agenda, Sept. 29, 2026, 2:00 p.m. session, Item 28 (Advance Kern agreement with Pacific Steel Group, PSGM3 LLC), Kern County Board of Supervisors, Sept. 29, 2026.
  2. Pacific Steel Group presentation heard at Mojave Chamber Meeting, Mojave Desert News, March 2, 2026.
  3. Mojave Micro Mill by PSGM3 Holdings Corp (Pacific Steel Group), NOP, SCH 2022100646, CEQAnet, Oct. 28, 2022.
  4. Mojave Micro Mill, Draft EIR, SCH 2022100646, CEQAnet, Nov. 17, 2023.
  5. Mojave Micro Mill, Notice of Determination (Board approval March 19, 2024), CEQAnet, March 21, 2024.
  6. Electrified Steel Mill Long Duration Energy Storage Demonstration, Notice of Determination, CEQAnet, Feb. 13, 2025.
  7. Mojave Micro Mill Project, Incidental Take Permit No. 1927-ITP-2024-073-04, Notice of Determination, CEQAnet, Jan. 31, 2025.
  8. Mojave Micro Mill Project, Amendment No. 1 to Incidental Take Permit, Notice of Determination, CEQAnet, March 19, 2025.
  9. Notice of Availability for Public Review and Hearing, Mojave Micro Mill Draft EIR, Kern County Planning and Natural Resources Department, November 2023.
  10. Notice of Determination, Mojave Micro Mill (case numbers and approval), Kern County, March 2024.
  11. PSG Mojave Micro Mill NOP and Initial Study, Kern County Planning and Natural Resources Department, October 2022.
  12. Mojave Micro Mill Project (environmental documents and hearing staff reports), Kern County Planning and Natural Resources Department.
  13. Business meeting item: PSGM3, LLC, agreement LDS-24-002, California Energy Commission, Jan. 21, 2025.
  14. California Competes Tax Credit Committee meeting minutes, Governor’s Office of Business and Economic Development, April 25, 2024.
  15. California’s economy forges ahead: Pacific Steel breaks ground on state’s first new steel mill in 50 years, Office of Gov. Gavin Newsom, March 7, 2025.
  16. Discover Our Mojave Micro Mill, Pacific Steel Group.
  17. PSG Breaks Ground on California’s 1st Steel Mill in 50 Years, Pacific Steel Group, March 2025.
  18. Pacific Steel Group Selects Danieli For New Micro Mill, Pacific Steel Group, April 5, 2022.
  19. Pacific Steel Group home page, Pacific Steel Group.
  20. County Planning Commission recommends approval of proposed $5.4 million steel plant near Mojave, Tehachapi News, Feb. 9, 2024.
  21. Kern supervisors approve permits for first California steel mill in decades, Tehachapi News, March 20, 2024.
  22. Supervisors approve steel mill expected to bring more than 400 jobs to Mojave area, Mojave Desert News, March 21, 2024.
  23. Processing 400 000 tonnes of steel scrap in the Mojave Desert, Recycling International, March 19, 2026.
  24. Danieli Working On First California Steel Mill in 50 Years, Construction Equipment Guide, July 7, 2025.
  25. Pacific Steel Group in Mojave navigating impact of tariffs, 23ABC News (KERO), June 18, 2025.
  26. Steel mill breaks ground in Mojave, Antelope Valley Press, March 7, 2025.
  27. California’s first steel mill in 50 years breaks ground in Kern County, BakersfieldNow (KBAK/KBFX), March 6, 2025.
  28. Pacific Steel Group Sues Commercial Metals for Monopolization of California Steel Rebar Market, For Construction Pros, Nov. 3, 2020.
  29. Texas rebar giant CMC gets hit with $110M anti-trust verdict in lawsuit with Pacific Steel Group, Fastmarkets, Nov. 12, 2024.
  30. CMC Statement Regarding Pacific Steel Group v. Commercial Metals Co. Litigation, Commercial Metals Co. via PR Newswire, Nov. 5, 2024.
  31. Commercial Metals To Appeal Adverse Ruling In Pacific Steel Litigation, Nasdaq (RTTNews), Sept. 30, 2025.
  32. Regional brokerage market reports (Bakersfield industrial, Q2 2026).
  33. Regional brokerage market reports (Bakersfield industrial, July 2026).
  34. National brokerage market reports (U.S. industrial, July 29, 2026).
  35. AdvanceKern: Kern County Business Recruitment & Job Growth Incentive Initiative, County of Kern.
  36. Kern County unveils new robust economic incentive program, Tejon Ranch Co., November 2017.
  37. Kern County offering incentives to lure more industries, BakersfieldNow (KBAK/KBFX), Aug. 3, 2018.

About this article

Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.

Featured image: hot-rolled steel at a steel mill, shown for illustration, not the Mojave Micro Mill. Photo by Robert Kerton, CSIRO, Wikimedia Commons, CC BY 3.0.