RB Inyokern Data Center: What the 99 MW Proposal Means for Kern County

R&L Capital’s 238,000-square-foot AI data center is working through a state power plant exemption while Ridgecrest, water agencies and labor groups weigh in.

The RB Inyokern Data Center is a proposed AI data center on about 50 industrially zoned acres near US 395 and State Route 178 in unincorporated Inyokern, Kern County, California. R&L Capital, Inc. of Trona plans a 238,000-square-foot building with 40 diesel generators providing up to 99 MW of backup power. The California Energy Commission (CEC) is reviewing its Small Power Plant Exemption request (docket 26-SPPE-01). The commission has not decided.

Key takeaways

  • R&L Capital applied to the CEC in April 2026 (docket 26-SPPE-01) for a Small Power Plant Exemption covering a 238,000-square-foot data center with 99 MW of diesel backup generation.
  • The Ridgecrest City Council authorized an intervenor petition on July 15, 2026, and the CEC docketed it July 20. The city says it has not taken a position for or against the project.
  • CEC staff issued Data Requests Set 2 on Sept. 25, 2026, with responses due in 30 days. No hearing or decision date has been set.
  • R&L estimates operating water demand at 36.83 to 49.10 acre-feet a year. The Indian Wells Valley Water District calls the groundwater basin critically over-drafted.
  • The four parcels were Phase II of R&L’s 2017 solar proposal, but the 26.6 MW solar project Kern County approved on March 23, 2021, did not include them.

RB Inyokern Data Center at a glance

ItemDetail
ProjectRB Inyokern Data Center (RBIDC)
LocationNear US 395 and State Route 178, Inyokern (unincorporated Kern County); listed as 6260 CA-178. APNs 084-010-43, 084-010-44 and portions of 084-010-45 and 084-010-48
Applicant/ownerR&L Capital, Inc., Trona (CEO Robbie Barker); a brokerage is marketing the project to investors
JurisdictionCalifornia Energy Commission (Small Power Plant Exemption); Kern County (land use)
Case numbersCEC Docket 26-SPPE-01; Kern County file referenced as PLN25-0268 in applicant filings
SizeAbout 50 acres of 83.16 total; single-story building of about 238,000 SF, 30 ft maximum height; about 70 MW IT load in six data halls; 99 MW total demand
UseAI and high-performance computing data center; 40 diesel generators of 3 MW each for emergency backup only
StatusUnder CEC review; Data Requests Set 2 issued Sept. 25, 2026; Ridgecrest intervenor petition filed July 20, 2026
Next stepApplicant responses to Data Requests Set 2 (30-day window, late October 2026); CEC environmental document and hearing not yet scheduled

What is the RB Inyokern Data Center?

The RB Inyokern Data Center (RBIDC) is a single-story building of about 238,000 square feet, no taller than 30 feet, proposed by R&L Capital on roughly 50 acres, according to the California Energy Commission project page. The applicant’s sustainability plan describes six data halls with about 70 MW of IT load, built for AI and high-performance computing.

The state is involved because of the backup power. The plan calls for 40 diesel generators of 3 MW each, in two yards of 20, for utility outages only and not connected to the grid. All would carry Tier 4 Final emissions controls. Because the backup plant is under 100 MW, R&L applied for a Small Power Plant Exemption instead of a full CEC license. Forty 3 MW units equal 120 MW of nameplate capacity, so CEC staff asked for the power-limiting design that would hold output to 99 MW.

Grid power would come from Southern California Edison through a new on-site 115/34.5 kV substation. The applicant says SCE’s Method of Service (MOS174), dated March 30, 2026, confirms 99 MW of demand. SCE would build new subtransmission lines and expand its Inyokern Substation.

Cooling would use hybrid cooling towers and water-cooled chillers. R&L estimates operating demand at 36.83 to 49.10 acre-feet a year, or about 12 to 16 million gallons. The Inyokern Community Services District would supply it after annexation, per the sustainability plan. CEC staff’s first data requests note an on-site well for emergencies.

In a community letter signed by Barker, R&L cites a $250 million investment, more than 1,600 construction jobs over about four years, 30 to 60 permanent jobs and more than $6 million a year in tax revenue. The applicant targets construction in the second quarter of 2027, a 48-month build and permanent 99 MW service in 2029 or later. DCD reported a 60 MW first phase.

Where is the RB Inyokern Data Center site?

The site is near US 395 and State Route 178 in the Indian Wells Valley. DCD places the campus between US 395 on the east and North Brown Road on the west. A brokerage investor listing gives the address as 6260 CA-178. The applicant’s thermal plume study puts the site 0.9 miles from Inyokern Airport. Sources describe the exact corner differently.

The four parcels total 83.16 acres. They are zoned M-2 PD (Medium Industrial, Precise Development), with an Inyokern Specific Plan designation of Service Industrial/Flood Hazard, according to Kern County application materials filed with the CEC. The land is vacant. R&L is asking the county for a Specific Plan Amendment to eliminate a 90-foot-wide future road reservation, plus a Conditional Use Permit for the data center.

What was planned for the same parcels in 2017?

R&L Capital planned solar on this land first. A July 2017 notice of preparation for the RB Inyokern Solar Project proposed 32 MW on 237.43 acres at the northeast corner of State Route 178 and Brown Road. It listed the four data center parcels as Phase II.

By the draft EIR in July 2020, the solar project had shrunk to 26.6 MW on 166.5 acres, and its parcel list no longer included those parcels. The Board of Supervisors approved it on March 23, 2021, with two Conditional Use Permits and a Specific Plan Amendment removing part of a planned collector road. The data center request follows a similar path: industrial zoning already in place, plus an amendment to drop a planned road.

Who is R&L Capital, the company behind the Inyokern data center?

R&L Capital, Inc. lists an address on Trona Road in Trona, in San Bernardino County. A 2015 company release identified Robbie Barker as CEO of Valley Wide Construction Services, also in Trona. CEC filings list Kyle Mohr as applicant representative, and KGET identified attorney Sean Hungerford as R&L’s counsel.

Valley Wide is an industrial construction and maintenance contractor with a 20,000-square-foot fabrication shop and a crane fleet, per that release. Barker has also pursued small solar projects near Trona in Inyo County. They include the 2 MW Trona 3 project, approved in 2018 per its decommissioning plan, and two more totaling 4.2 MW that went through recirculated review in 2023.

The data center is a bigger leap. A brokerage is marketing it to investors under the headline “99 MW CONFIRMED” and is acting as agent for interested investor-principals, per Roadrunner395. R&L’s letter calls the project “not a speculative venture.” No tenant has been named in public filings, and Barker did not respond to inquiries from SJV Water.

What does the RB Inyokern Data Center mean for the Kern County market?

It shows that power, not warehouse demand, can now drive industrial land interest in East Kern. No major brokerage tracks Kern County as a data center market, so the benchmarks are national. A national brokerage’s North America data center report for the first half of 2026 (Aug. 27, 2026) put U.S. data center vacancy at a record-low 1.4%, with 7,481.1 MW under construction and 80.4% of it preleased. A second national brokerage’s midyear 2026 data center report (Aug. 11, 2026) said vacancy has held at 1% for a third straight year, with more than 66 GW under construction and 77% of it in frontier markets.

A 2026 global data center market comparison from a third national brokerage says “power is still the primary constraint across global data center markets.” Its 2026 data center development cost guide puts average greenfield costs at $17.6 million per MW, with capital moving toward secondary, tertiary and frontier markets.

That is the Inyokern pitch in one word: power. The investor listing leads with an issued Method of Service and “Zero Grid Upgrades Required,” and it states SCE can support 99 MW by 2029. The first national report calls power availability and infrastructure delivery timelines “the most decisive factors” in site selection. For Kern owners, industrial land near a substation with confirmed capacity can now draw interest beyond logistics and solar users. Our guides to industrial power requirements and SB 410 energization timelines explain what that capacity involves.

Two cautions apply. At the cost guide’s average, a 70 MW IT build would run well past R&L’s $250 million figure, and it is not clear what the number covers. The same national report also warns that “community engagement is now a development constraint on par with power procurement.” A 275 MW data center campus is also planned in the Elk Hills Oil Field in western Kern (see our Elk Hills data center article). Inyokern is an early test of how these projects fare here.

Why did Ridgecrest intervene in the Inyokern data center review?

Ridgecrest wants a formal role in the hearings and the evidentiary record without taking a side. The City Council took up agenda item 19 on July 15, 2026, and reached consensus to seek intervenor status. The petition, filed by Adam Nir of Aleshire & Wynder, LLP, was docketed July 20.

City Manager Travis Reed told the council, “This simply gives us a seat at the table,” South Kern Sol reported. The petition says the city “has not reached a position regarding support or opposition of the Project.” It lists water, transmission capacity, greenhouse gases, infrastructure, economic development and cumulative impacts.

The point for East Kern growth is power. In the petition’s words, “The proposed interconnection is within the same substation that provides power to a majority of City residents and the Naval Air Weapons Station at China Lake.” The city argues that using up finite transmission capacity could limit future housing and economic development.

What water and other concerns are on the record?

Water is the most common objection. The Indian Wells Valley Water District wrote Aug. 12 that the basin is “designated as a critically over-drafted basin.” It noted that the Inyokern CSD’s annual groundwater allotment is 102 acre-feet and that a state assessment lists the CSD as a “Disadvantaged and Failing System.” The basin is also under adjudication in Orange County Superior Court.

Outside estimates run far higher. SJV Water reported that a formula from a 2021 study would imply roughly 1,822 acre-feet a year at 99 MW. Scale is another question. Roadrunner395 reported that R&L expected a second Method of Service adding 99 MW by 2030 to 2031. KGET reported that R&L’s attorney said only one data center is proposed.

Other filers include Naval Air Weapons Station China Lake, citing “initial mission concerns,” the Indian Wells Valley Airport District and Sierra Sands Unified School District. The Eastern Kern County Resource Conservation District and Kerncrest Audubon Society filed in opposition. The Indian Wells Valley Groundwater Authority voted June 10 to send the CEC a water letter. From Aug. 27 to Sept. 25, more than 20 docketed comments carried the title “Full EIR Request.”

Support comes mainly from labor. The State Building and Construction Trades Council of California wrote May 22 that the project “will generate substantial employment opportunities for California’s skilled construction workforce.” It said it has a Letter of Agreement with the applicant framing a Project Labor Agreement. IBEW Local 428 members filed letters, and DCD reported Kern Economic Development Corporation’s endorsement.

What is CEC staff asking?

Staff’s second data requests, issued Sept. 25, seek air and health risk modeling files, cultural surveys, gen-tie routes, SCE workforce estimates and public service response times. Staff also noted that engine specifications indicate full-load CO2 emissions above 4,400 pounds per hour, about three times the applicant’s 1,451, and asked for documentation.

What happens next for the RB Inyokern Data Center?

The next step is R&L’s response to staff’s second data requests, due in late October 2026.

  • Late October 2026: R&L’s responses to Data Requests Set 2 are due 30 days after the Sept. 25 request.
  • CEC environmental review: No CEQA document, hearing or decision date has been posted. The applicant had targeted a decision about 180 days after its April filing.
  • Ridgecrest’s petition: South Kern Sol reported July 23 that the CEC had not ruled. No ruling has been docketed.
  • Kern County: Even with an exemption, the project needs the county Specific Plan Amendment and Conditional Use Permit, plus annexation into the Inyokern CSD. SJV Water also reported it needs approval from the Indian Wells Valley Groundwater Authority. No county hearing date has been set.
  • Construction: Targeted for the second quarter of 2027, with a 48-month build.

State policy is moving too. Roadrunner395 reported that Gov. Gavin Newsom signed seven data center bills on Sept. 21, 2026, aimed at electricity costs and tracking energy and water use. For another East Kern heavy-industry project, see our article on the Mojave Micro Mill incentive.

Frequently asked questions

What is the RB Inyokern Data Center?

It is a proposed AI and high-performance computing data center in unincorporated Inyokern, near US 395 and State Route 178. R&L Capital plans a single-story, 238,000-square-foot building on roughly 50 acres. Plans call for about 70 MW of computing load, 99 MW of total demand from Southern California Edison and 40 diesel backup generators.

Who is developing the Inyokern data center?

The applicant and owner is R&L Capital, Inc., based in Trona in San Bernardino County. A 2015 company release identified its CEO, Robbie Barker, as CEO of Trona-based contractor Valley Wide Construction Services. A brokerage is marketing the project to investors. R&L proposed solar on these parcels in 2017 and won county approval for a smaller solar project nearby in 2021.

How much water would the Inyokern data center use?

R&L estimates 36.83 to 49.10 acre-feet a year, or roughly 12 to 16 million gallons, supplied by the Inyokern Community Services District after annexation. The Indian Wells Valley Water District says that district’s yearly groundwater allotment is only 102 acre-feet and that the basin is critically over-drafted. Some opponents argue real use could run much higher.

What is a Small Power Plant Exemption?

It lets a thermal power facility under 100 MW skip the California Energy Commission’s full licensing process. The commission must find, after CEQA review, that the plant will not cause substantial adverse environmental or energy impacts. Here the exemption would cover the data center’s diesel backup plant. Local permits, in this case from Kern County, are still required.

Why did Ridgecrest file to intervene?

The City Council authorized the petition on July 15, 2026, and the CEC docketed it July 20. The city says it has no position yet. It wants a formal voice on groundwater, transmission capacity, greenhouse gases and cumulative effects. The project would tie into the substation that serves most Ridgecrest residents and Naval Air Weapons Station China Lake.

When will the Energy Commission decide on the Inyokern data center?

No hearing or decision date has been set. Staff issued a second set of data requests on Sept. 25, with answers due in about 30 days. Staff must then finish its CEQA review before the commission can act. The applicant had hoped for a decision about 180 days after its April 2026 filing.

Does Kern County have to approve the Inyokern data center?

Yes. Even if the CEC grants the exemption, R&L needs a Kern County Specific Plan Amendment to remove a 90-foot future road reservation. It also needs a Conditional Use Permit for a data center in the M-2 zone and annexation into the Inyokern Community Services District for water. No county hearing date has been set.

Own industrial land near a substation in East Kern, or wondering how this project could affect nearby property values and leasing? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us. Get Kern County CRE news monthly: subscribe to the Kern CRE report.

Sources

  1. RB Inyokern Data Center (project page), California Energy Commission.
  2. Docket Log, 26-SPPE-01, California Energy Commission, generated Sept. 27, 2026.
  3. Environmental Sustainability Plan and Best Management Practices, SPPE Application Appendix O (TN 269666), R&L Capital, Inc., docketed April 28, 2026.
  4. RB Inyokern Data Center SPPE Application, Appendix E, thermal plume analysis (TN 269605), R&L Capital, Inc., docketed April 23, 2026.
  5. RB Inyokern Data Center Data Requests Set 1 (TN 270553), California Energy Commission, June 11, 2026.
  6. RBIDC Data Response Set 1 (TN 271129), R&L Capital, Inc., July 1, 2026.
  7. Appendix N Supplement, Section N4: Kern County Specific Plan Amendment and CUP applications (TN 271099), R&L Capital, Inc., June 29, 2026.
  8. City of Ridgecrest Petition to Intervene (TN 271564), City of Ridgecrest and Aleshire & Wynder, LLP, July 20, 2026.
  9. Indian Wells Valley Water District Comments (TN 271977), Indian Wells Valley Water District, Aug. 12, 2026.
  10. SBCTC Support for the RB Inyokern Data Center Project (TN 270195), State Building and Construction Trades Council of California, May 22, 2026.
  11. NAWS China Lake Mission Concerns (TN 270501), Naval Air Weapons Station China Lake, June 10, 2026.
  12. Data Requests Set 2 for RB Inyokern Data Center, 26-SPPE-01 (TN 272947), California Energy Commission, Sept. 25, 2026.
  13. City Council Agenda, July 15, 2026 (Item 19), City of Ridgecrest, July 15, 2026.
  14. Ridgecrest moves forward with intervener petition in Inyokern data center review, South Kern Sol, July 16, 2026.
  15. Ridgecrest petitions to intervene in review of Inyokern data center, South Kern Sol, July 23, 2026.
  16. ‘We don’t want it:’ Ridgecrest residents continue to push back against proposed data centers, labor groups say not so fast, KGET, June 4, 2026.
  17. Ridgecrest city council to submit request for intervener status over possible data center, KGET via AOL, July 16, 2026.
  18. Water a big question for proposed AI data center in eastern Kern desert, SJV Water, May 8, 2026.
  19. MEETING NOTES: Desert groundwater agency seeks information on proposed AI data center, SJV Water, June 15, 2026.
  20. AI Data Center Environmental Review: Proposed Inyokern Data Center Highlights Water Use Concerns, Somach Simmons & Dunn, May 21, 2026.
  21. 99MW data center proposed in Kern County, California, DCD, July 6, 2026.
  22. SAY IT ISN’T SO! An AI Data Center is Coming to Downtown Inyokern? (with updates), Roadrunner395, April 26, 2026, updated Sept. 21, 2026.
  23. A Positive Future for Eastern Kern, R&L Capital, Inc. (hosted by Roadrunner395), April 2026.
  24. Regional brokerage market reports (data center).
  25. Notice of Preparation and Initial Study, RB Inyokern Solar Project by R&L Capital, Inc., Kern County Planning and Natural Resources Department, July 2017.
  26. RB Inyokern Solar Project by R&L Capital, Inc., Draft EIR, CEQAnet (Kern County, SCH 2017071020), July 2, 2020.
  27. RB Inyokern Solar Project Draft EIR, Volume 1 Executive Summary, CEQAnet (Kern County, SCH 2017071020), July 2020.
  28. Notice of Determination, RB Inyokern Solar Project (Board approval March 23, 2021), CEQAnet, March 24, 2021.
  29. SCH 2017071020 project document list, CEQAnet.
  30. Decommissioning Plan, Trona 3 Solar Project, Inyo County, March 2021.
  31. Recirculated CEQA public comments, Renewable Energy Permits 2022-01 and 2022-02, Inyo County, Aug. 25, 2023.
  32. Valley Wide Construction Specializes in Industrial Pipe Fabrications, Concrete Foundations, Crane Services and Rentals and Plant Outage Services, 24-7 Press Release, Sept. 30, 2015.
  33. National brokerage market reports (U.S. data center, Aug. 27, 2026).
  34. National brokerage market reports (U.S. data center, Aug. 11, 2026).
  35. Regional brokerage market reports (data center, 2026).
  36. Canada’s Beacon DC targets 275MW data center campus on California oil field, DCD, June 24, 2026.

About this article

Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.