Elk Hills Data Center: CRC and Beacon Plan a 275 MW AI Campus on 100 Acres of Oilfield Land

California Resources Corp. would supply the land and the power from its Elk Hills plant. Calgary-based Beacon Data Centers would build, own and operate the campus. The land terms are not public.

The Elk Hills data center, called the Golden Valley Technology Hub, is a proposed 400,000-square-foot AI data center on about 100 acres of California Resources Corp.’s Elk Hills oil field, roughly 20 miles west of Bakersfield in Kern County, California. Beacon Data Centers of Calgary would build, own and operate it on 275 megawatts (MW) from CRC’s Elk Hills Power Plant. CRC applied for a Kern County permit in June 2026. Land terms have not been disclosed.

Key takeaways

  • California Resources Corp. (CRC) and Beacon Data Centers unveiled the 275 MW Golden Valley Technology Hub in June 2026 on about 100 acres of the Elk Hills oil field.
  • Power would come from CRC’s 550 MW natural gas-fired Elk Hills Power Plant, in operation since 2003, with no utility grid upgrades required, according to the project.
  • CRC applied for a Kern County conditional use permit in mid-June 2026, which starts an environmental review it expects to take about two years.
  • The Bakersfield Californian reported about 1,500 workers at the construction peak and as many as 250 permanent jobs, with about 6,000 gallons a year of cooling-water top-offs.
  • Whether Beacon will buy or ground-lease the 100 acres has not been disclosed.

Deal at a glance

ItemDetail
ProjectGolden Valley Technology Hub
LocationElk Hills oil field, western Kern County, about 20 miles west of Bakersfield and north of Taft
LandAbout 100 acres now used for oilfield operations
Landowner and power supplierCalifornia Resources Corp. (NYSE: CRC)
Data center developerBeacon Data Centers (Calgary), to build, own and operate the campus
Building400,000 SF data center, plus an electrical substation, office and parking
Power275 MW from the 550 MW Elk Hills Power Plant; backup batteries, fifteen 2.5 MW diesel generators and a utility grid connection for backup
Land termsNot disclosed (sale or ground lease not reported)
InvestmentNot disclosed; The Bakersfield Californian described a facility “costing easily 10 figures”
AnnouncedJune 2026
StatusKern County conditional use permit application filed June 2026; environmental review expected to take about two years; construction timing not set

What is the Elk Hills data center deal?

The Golden Valley Technology Hub pairs one company’s land and power with another company’s data center business. CRC owns and operates the Elk Hills oil field and its power plant. Beacon, a Calgary-based developer, would build, own and operate the data center, according to the project website. CRC’s second-quarter 2026 results describe it as “a proposed data center development in partnership with Beacon Data Centers (Beacon), at CRC’s Elk Hills field.”

The Bakersfield Californian first reported the plan on June 15, 2026, as CRC prepared to apply for a Kern County conditional use permit that would let the campus “receive 275 megawatts of surplus power from the company’s natural gas-fired Elk Hills Power Plant.” DatacenterDynamics and 23ABC followed on June 24. Some local coverage describes CRC as the developer and permit applicant. The project website says Beacon will build, own and operate the data center, with CRC supplying power. This article follows the project site and treats CRC as landowner, power supplier and permit applicant.

This is a land deal in substance, but the land terms are not public. Neither company has said whether Beacon will buy the roughly 100 acres, lease them or pay CRC through power sales instead. What is public is the program, the power source and the permit path.

Where is the Golden Valley Technology Hub?

The campus would sit in the Elk Hills oil field in western Kern County, about 20 miles west of Bakersfield and north of Taft. The site is about 100 acres “currently used for oilfield operations,” according to the project’s location page, and the Californian placed it on “an existing industrial site a mile and a half from the nearest home.” The plan calls for a 400,000-square-foot data center, an electrical substation, an office and a parking lot.

Those numbers say a lot about the land. By our arithmetic, a 400,000-square-foot building on 100 acres covers only about 9% of the site, far less than a typical warehouse parcel uses. The value is not in building area. It is in power: at 275 MW, the campus would draw about 2.75 MW per acre.

Who is behind it: CRC and Beacon Data Centers

CRC is the landowner and power supplier, and Beacon is the data center developer. DatacenterDynamics describes CRC as California’s largest oil and gas exploration company, and the Californian reports it is already Kern County’s largest property taxpayer. DCD reported that the Elk Hills Power Plant is a 550 MW natural gas plant that has operated since 2003. In the second quarter of 2026, CRC also reached first carbon dioxide injection at Carbon TerraVault I, which it calls California’s first carbon capture and storage project. “Our team continued to advance the Golden Valley Technology Hub with Beacon, leveraging CRC’s assets to meet California’s growing AI demand for reliable power,” CEO Francisco Leon said in the Aug. 10, 2026 release.

Beacon’s co-founder told the Californian that the company formed in 2023. DCD reports that investment firm Nadia Partners launched Beacon in March 2023 and that its portfolio includes more than 10 campuses representing 6 GW of planned capacity in Alberta, New Brunswick, Texas, Alabama, Ohio and Kern County. No end user for Elk Hills has been named. CRC’s chief sustainability officer, Chris Gould, told 23ABC that “Kern County has all the right ingredients” for a data center.

Why is oilfield land with on-site power valuable for data centers?

Power is the scarce input, and Elk Hills comes with its own. A national brokerage’s North America data center report for H1 2026 put primary-market vacancy at a record-low 1.4%, with 7,481.1 MW under construction and commitments on 80.4% of it. The report says “power availability and infrastructure delivery timelines remain the most decisive factors influencing site selection, leasing activity and pricing.” It adds that developers now weigh grid power against behind-the-meter solutions, meaning power produced on site.

Elk Hills offers the behind-the-meter version. The project says power would come from “an existing, on-site power plant, with all associated infrastructure costs paid for by the project developers,” and its FAQ says the campus “would not require upgrades to the utility electrical grid.” That sidesteps the interconnection queues that slow many data center sites. Our guide to industrial building power requirements explains why those timelines matter.

The site also brings what the project calls “existing oil, gas, water, power generation and electrical infrastructure, industrial land uses,” plus fiber access and a trained workforce. For CRC, the deal would turn surplus generating capacity and already-disturbed industrial acreage into a long-term customer. How CRC will be paid, through power sales, land rent, a sale price or some mix, has not been disclosed.

Water is the other usual objection, and the design addresses it. The Californian reported a closed-loop system needing an initial fill of about 600,000 gallons and top-offs of about 6,000 gallons a year. The project compares that with evaporative designs that use millions of gallons per day.

Ground lease or sale: how are data center land deals usually structured?

Data center land deals usually take one of three forms: a fee sale, a ground lease or a power-led deal. Because the Elk Hills terms are not public, the table shows general practice only. The project website says Beacon would own the data center, which fits either a land purchase or a long-term ground lease. For more on the lease option, see our explainer on ground leases.

StructureHow it worksWhy a landowner might prefer itWhy a developer might prefer it
Fee saleDeveloper buys a carved-out parcel and owns land and buildingCash at closing; no long-term exposure to the tenantSimplest to finance; full control of the site
Ground leaseLandowner keeps title; developer owns the building and pays rent for decadesKeeps control of land inside an active oil field; rent plus reversion at the endLower upfront cost; capital goes to buildings and equipment
Power-led dealLand terms are secondary to a long-term power supply contractMonetizes generating capacity at a stable priceFirm power on a known timeline

General market practice, not the Elk Hills terms, which have not been disclosed.

Two features of this site point toward a structure that keeps CRC in control. The campus sits inside a working oil field with wells, pipelines and access roads around it, and it depends on a CRC-operated plant for power. A sale would require easements for access, power lines and safety buffers. A ground lease handles those inside one document.

Any ground lease would also have to be financeable. Lenders funding a 10-figure building on leased land look for a term that outlasts the loan, plus leasehold mortgage protections. The Californian reported a facility lifespan of 20 to 25 years, which gives a sense of the horizon both sides are pricing.

What permits does the Elk Hills data center need?

The main approval is a Kern County conditional use permit, and several state and regional permits run alongside it. CRC applied in mid-June 2026, and the Californian reported that the application “triggers a two-year environmental review CRC expects will proceed concurrent with its pursuit of water, air quality and other permits.” The project’s FAQ confirms review under the California Environmental Quality Act and says “Construction timing has not yet been determined.” The project materials do not list a county case number. Our guide to entitlements and CEQA in Kern County explains the steps.

The state energy agency may play a smaller role here than in the Inyokern data center case. The California Energy Commission has “exclusive authority to certify all thermal power plants 50 megawatts (MW) and larger”. The RB Inyokern data center needed a Commission exemption because its backup generators total 99 MW. Elk Hills plans 15 diesel generators of 2.5 MW each, or 37.5 MW, which is below that threshold by our math. Public materials do not say whether the existing power plant’s certification needs any change to serve the data center.

The diesel generators will still need air permits, which in western Kern means the San Joaquin Valley Air Pollution Control District. The Californian also reported that the review could lead to mitigation such as sound barriers.

What does the Elk Hills data center mean for Kern County real estate?

Kern County now has two data center proposals in review: the 99 MW Inyokern project in the east and the 275 MW Elk Hills campus in the west. Both are selling the same thing, available power. Both show that land near firm electricity can draw buyers and tenants who never looked at Kern County for logistics or solar.

The tax stakes are large. The Californian described a facility “costing easily 10 figures,” and CRC declined to estimate the effect on its property tax bill. As a general guide, under Proposition 13’s 1% base rate, every $1 billion of assessed value produces roughly $10 million a year in base property tax before voter-approved add-ons. That is an illustration, not a CRC estimate. See our guide to Prop 13 reassessment for how assessed value is set.

The project would employ about 1,500 workers at the construction peak and as many as 250 in permanent roles, per the Californian.

What happens next?

  • Environmental review: the county review would include a Notice of Preparation or initial study and public comment periods. CRC expects about two years of review.
  • Construction: the Californian reported a year-long build once approved. The project says timing has not been set.
  • End user: Beacon has not named a tenant or hyperscaler (a very large cloud and AI company) for the campus.
  • Deal terms: CRC’s future SEC filings may disclose how the land and power arrangement is structured.
  • Other permits: water and air quality permits run alongside the county review.

Frequently asked questions

What is the Golden Valley Technology Hub?

It is a proposed AI data center on about 100 acres of California Resources Corp.’s Elk Hills oil field in western Kern County. Beacon Data Centers would build, own and operate a 400,000-square-foot facility with a substation, office and parking. CRC’s Elk Hills Power Plant would supply 275 MW, and the project was announced in June 2026.

Where is the Elk Hills data center?

The site is in the Elk Hills oil field, about 20 miles west of Bakersfield and north of Taft. The roughly 100 acres are used for oilfield operations today. The Bakersfield Californian reported that the nearest home is about a mile and a half away.

Did CRC sell or lease the land to Beacon Data Centers?

Neither company has said. It is unclear whether Beacon will buy the acreage, ground-lease it or rely mainly on a power supply contract. Beacon’s ownership of the data center fits either a purchase or a long-term lease.

Where will the Elk Hills data center get its power and water?

Power would come from CRC’s 550 MW natural gas-fired Elk Hills Power Plant, with 275 MW dedicated to the campus and no utility grid upgrades required, according to the project. Backup includes batteries, 15 diesel generators and a grid connection. Cooling would use a closed-loop system with about 600,000 gallons to fill and roughly 6,000 gallons a year in top-offs.

When could construction start on the Elk Hills data center?

No date is set. CRC expects the county environmental review to take about two years, alongside water and air permits. The Bakersfield Californian reported that building would take about a year after approvals.

How many jobs would the Elk Hills data center create?

The Bakersfield Californian reported about 1,500 construction workers at the peak and as many as 250 full-time permanent workers, from janitorial to specialized engineering roles. CRC declined to estimate how much the project would add to its annual property tax payment. It is already Kern County’s largest property taxpayer.

Own land in Kern County with power, rail or freeway access and wondering what it could be worth to a new kind of user? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us. Get Kern County CRE news monthly: subscribe to the Kern CRE report.

Sources

  1. The Bakersfield Californian, CRC proposes W. Kern data center with dedicated power, closed-loop cooling, The Bakersfield Californian, June 15, 2026.
  2. DatacenterDynamics, Canada’s Beacon DC targets 275MW data center campus on California oil field, DatacenterDynamics, June 24, 2026.
  3. 23ABC (KERO), Massive AI data center proposed for Kern County’s Elk Hills, June 24, 2026.
  4. California Resources Corporation, California Resources Corporation Reports Second Quarter 2026 Financial and Operating Results, GlobeNewswire, Aug. 10, 2026.
  5. Golden Valley Technology Hub, Project website (home, location and FAQ pages).
  6. Taft Midway Driller, CRC proposes data center on Elk Hills, June 17, 2026.
  7. California Energy Commission, RB Inyokern Data Center (project page).
  8. National brokerage market reports (U.S. data center, Aug. 27, 2026).

About this article

Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.