State wildlife officials amended the project’s western Joshua tree permit a fourth time, giving Clearway more time to record a conservation easement. Here is what was approved, what is built and what comes next.
The Rosamond South Solar Project is a Clearway Energy Group solar and battery plant about six miles southwest of Rosamond in unincorporated Kern County, California. Kern County supervisors approved it Dec. 13, 2022, for up to 165 MW of solar and 245 MW (980 MWh) of storage on about 1,302 acres. On Aug. 17, 2026, the California Department of Fish and Wildlife (CDFW) approved Amendment No. 4 to the project’s western Joshua tree take permit.
Key takeaways
- Kern County supervisors approved the Rosamond South Solar Project on Dec. 13, 2022, for up to 165 MW of solar and 980 MWh of storage on about 1,302 acres across 66 private parcels.
- On Aug. 17, 2026, CDFW approved Amendment No. 4 to the project’s western Joshua tree permit. It changes a tree preservation condition and extends the deadline to record a conservation easement.
- The permit covers incidental take of 1,354 western Joshua trees. Three earlier amendments moved the count from 1,346 in February 2024 to as high as 1,371 in March 2025.
- Clearway’s Rosamond South 1, the first part built, with 140 MW of solar and 117 MW of storage, reached commercial operation in November 2025.
- Clearway says its Kern County plants total more than 1,500 MW and together pay over $20 million a year in property taxes.
Rosamond South Solar Project at a glance
| Item | Detail |
|---|---|
| Project | Rosamond South Solar Project (built portion operating as Rosamond South 1, announced as the Rosamond South Energy Center) |
| Location | About 6 miles southwest of Rosamond, unincorporated Kern County; project area bounded by Rosamond Boulevard (north), 90th Street West (east), West Avenue A (south) and 170th Street West (west); ZIP 93501 |
| Applicant and owner | Golden Fields Solar IV, LLC, a subsidiary of Clearway Energy Group LLC |
| Jurisdiction | Kern County (lead agency for land use); California Department of Fish and Wildlife (responsible agency for the Joshua tree permit) |
| Case numbers | ZCC 18 and CUP 16 (Map 233); SPA 31, SPA 33, ZCC 43, CUP 40, CUP 44 and CUP 46 (Map 232); SPA 40, ZCC 157 and CUP 120 (Map 231); WJTCA ITP No. 1927-ITP-2023-018-04; SCH No. 2021060079 |
| Size | About 1,302 acres on 66 parcels in four sites; up to 165 MW-AC of solar; up to 245 MW (980 MWh) of storage |
| Use | Solar PV and battery storage with substations and a 230 kV gen-tie line to the Teddy Substation or Southern California Edison’s Whirlwind Substation (per the Draft EIR) |
| Status | Entitled Dec. 13, 2022; Rosamond South 1 (140 MW solar, 117 MW storage) operating since November 2025; Joshua tree permit Amendment No. 4 approved Aug. 17, 2026 (notice filed Aug. 18) |
| Next step | Record the required conservation easement by the extended deadline (date not stated in the public notice); a second phase on the remaining entitlement has not been announced |
What did the state approve for the Rosamond South Solar Project in August 2026?
CDFW approved Amendment No. 4 to the project’s incidental take permit under the Western Joshua Tree Conservation Act, permit No. 1927-ITP-2023-018-04, on Aug. 17, 2026. The agency filed its notice of determination with the State Clearinghouse on Aug. 18.
This is a wildlife permit, not a new land-use approval. Amendment No. 4 “amends the WJT Preservation Condition of Approval and extends the deadline for recordation of the conservation easement.” WJT is the western Joshua tree. The amendment does not change the project’s size or the 1,354-tree count.
CDFW acted as a responsible agency, relying on the environmental impact report (EIR) Kern County prepared for the project. The notice does not give the old or new easement deadline, the easement’s acreage or its location. Those terms sit in the permit itself, which is not posted with the notice.
How many times has the Joshua tree permit been amended?
Four times. The western Joshua tree is protected under the Western Joshua Tree Conservation Act and the California Endangered Species Act. CDFW’s September 2026 notice for the Discovery Solar project describes the tree as a state candidate for listing. The CEQAnet notices show how the Rosamond South permit has changed:
| Permit action and date | Western Joshua trees covered |
|---|---|
| Original permit, approved Feb. 23, 2024 | 1,346 |
| Amendment No. 1, approved Nov. 7, 2024 | 1,347, adding one live Class B tree |
| Amendment No. 2, approved March 26, 2025 | 1,371 |
| Amendment No. 3, approved July 2, 2025 | 1,354, adding 229 trees and removing 246 |
| Amendment No. 4, approved Aug. 17, 2026 | 1,354; revises the preservation condition and extends the easement deadline |
Why did the tree count keep moving?
The changes track construction. CDFW issued the original permit in February 2024, about six months before Clearway started building in August 2024, Solar Power World reported. Amendments followed in November 2024, March 2025 and July 2025 while the first phase was under construction. The notices do not explain why trees were added or dropped.
What is the Rosamond South Solar Project?
It is a county-approved solar and battery site on private desert land southwest of Rosamond. The Kern County Board of Supervisors approved it on Dec. 13, 2022, and adopted a statement of overriding considerations. That step means the board found the project’s benefits outweighed environmental effects that could not be fully avoided. The notice describes about 165 MW of solar and about 980 MWh of storage, roughly four hours at full output, on about 1,302 acres across 66 parcels in four sites.
The plan grew during review. The county’s June 2021 Notice of Preparation described up to 154 MW of solar and 200 MW of storage on about 1,292 acres and 64 parcels. The Draft EIR, released July 13, 2022, raised that to 165 MW and 245 MW (980 MWh). The Planning Commission heard the project Oct. 13, 2022, per the county project page, before the supervisors’ December vote.
What was in the entitlement package?
The approvals for the four sites were:
- Site 1 (Map 233): Zone Change Case 18 from E (2 1/2) RS FPS to A FPS and Conditional Use Permit 16 for solar with battery storage, on about 71 acres.
- Site 2 (Map 232): Specific Plan Amendments 31 and 33, including a change to the Willow Springs Specific Plan; Zone Change Case 43 on about 80 acres; CUP 40 for solar on about 241 acres; CUP 44 for a telecommunications tower; and vacations of public access easements.
- Site 3 (Map 232): Zone Change Case 43 on about 356 acres and CUP 46 for solar on about 551 acres.
- Site 4 (Map 231): Specific Plan Amendment 40 on about 365 acres, Zone Change Case 157 and CUP 120 for solar on about 440 acres, plus vacations of public access easements.
Where is the Rosamond South site, and what was there before?
The site lies in the Mojave Desert, bounded by Rosamond Boulevard on the north, 90th Street West on the east, West Avenue A on the south and 170th Street West on the west. CDFW places it about six miles southwest of the town of Rosamond, in the southeastern corner of unincorporated Kern County.
Before approval, much of the land carried estate residential zoning, E (2 1/2) RS and E (5) RS, with an FPS overlay. The zone changes moved those parcels to A FPS (Exclusive Agriculture), and use permits authorized the solar fields. The specific plan amendments and vacated access easements also point to land once planned for rural lots and roads, now combined into one energy site.
In a 2022 comment letter on the Draft EIR, CDFW said aerial imagery showed “undeveloped land that may have suitable habitat for special status species,” and it flagged the state-threatened desert tortoise.
Transmission is part of the site’s logic. The Draft EIR describes a 230 kV gen-tie line to either the Teddy Substation or Southern California Edison’s Whirlwind Substation. The proposed Euismod battery project, also tied to Whirlwind, sits on the northwest side of 170th Street West and Rosamond Boulevard, just beyond the project area’s northwest corner.
Who is behind Rosamond South?
Clearway Energy Group is behind it through a subsidiary. The applicant, Golden Fields Solar IV, LLC, is “a subsidiary of Clearway Energy Group LLC.” Clearway’s own materials tie the names together: Rosamond South 1 “is also referred to as Golden Fields Solar IV LLC by its offtakers,” the company said in its November 2025 release.
Clearway Energy Group “is owned by Global Infrastructure Partners and TotalEnergies,” per its company profile, and reports about 13.6 GW of gross capacity in 27 states.
Clearway began construction in August 2024, backed by a $550 million construction loan from a bank consortium of Societe Generale, ANZ, Siemens Financial Services, Commerzbank, CoBank, DNB and Nord/LB, Solar Power World reported. McCarthy Building Companies was the engineering, procurement and construction contractor. The build was expected to create more than 400 union jobs, with labor partners including Laborers Union 220 and IBEW Local 428.
Is the Rosamond South Solar Project built?
Partly. Clearway announced on Nov. 5, 2025, that Rosamond South 1 had reached commercial operations. The release describes a “117 MW energy storage and 140 MW solar complex” that will power more than 72,000 homes a year. Its buyers include MCE, the University of California, Rancho Cucamonga Municipal Utility, Eastside Power Authority, the City of Moreno Valley and Constellation Energy. The 2024 coverage described 15-year contracts.
That is less than the county approved: 140 of 165 MW of solar, and 117 MW of a 245 MW storage allowance. Federal plant data compiled by interconnection.fyi lists a planned 140 MW battery project named Rosamond South II, operated by Golden Fields Solar VI, LLC, with a proposed completion date of Nov. 1, 2026. No official source ties it to this entitlement, and Clearway has not announced it.
What does Rosamond South mean for Kern County real estate?
The project adds to a growing energy tax base, and it shows how desert land can change use. Rosamond South 1 brings Clearway’s operating footprint in Kern County to more than 1,500 MW of wind, solar and storage, “which together contribute over $20 million in property taxes to the county each year,” the company said. That figure covers all of Clearway’s Kern plants, not this project alone.
Timing matters for solar taxes. California’s property tax exclusion for new active solar energy systems covers systems installed by the end of 2026, and SB 710 lets them keep the break until the property sells, according to Sen. Catherine Blakespear. Rosamond South 1 came online in November 2025, inside that window. How much of its value stays off the roll is the county assessor’s call, and no figure has been published. For tax context, see our guide to the commercial solar tax credit after the OBBBA.
What about land: rezoned lots and mitigation acreage?
No major brokerage publishes solar land values or lease rates for the Kern side of the Antelope Valley. The county record shows the pattern instead: 66 private parcels, many zoned for estate homes, rezoned and combined into four solar sites with a path to a substation.
Joshua tree mitigation under the permit can be met through conservation easements recorded on land set aside from development. Our guide to industrial land entitlements and CEQA in Kern County explains the approval path.
What about industrial space and power?
Brokerage reports for Bakersfield are the closest benchmarks, and neither breaks out Rosamond. One Q2 2026 national brokerage report put industrial availability at 10.1%, with asking rent averaging $0.71 per square foot per month, triple net. Another regional brokerage report measured vacancy at 9.55%. Our primer on reading an industrial market report explains those terms.
Large solar builds bring short-term demand for laydown yards, equipment storage and lodging, then a smaller stream of service contractors. Power is also a site-selection factor. A national brokerage said power availability, reliability and costs “are increasingly shaping site selection, development feasibility and asset performance,” in a Feb. 26, 2026 release.
What happens next for the Rosamond South Solar Project?
The next step is paperwork, and then possibly more construction. Four items remain open:
- Conservation easement: Golden Fields Solar IV must record the easement by the extended deadline set in Amendment No. 4. The public notice does not give the date.
- Legal window: A CEQA challenge to a notice of determination generally must be filed within 30 days of the filing. For the Aug. 18 notice, that period runs into mid-September 2026.
- Second phase: Clearway has not announced plans for the unbuilt portion of the entitlement or for the Rosamond South II battery that federal data lists for Nov. 1, 2026.
- Neighbors: The Euismod battery project next to Whirlwind is set for a Kern County Planning Commission hearing on Oct. 22, 2026.
Frequently asked questions
What is the Rosamond South Solar Project?
It is a solar and battery storage plant about six miles southwest of Rosamond in unincorporated Kern County. Supervisors approved it on Dec. 13, 2022, for up to 165 MW of solar and 245 MW (980 MWh) of storage on about 1,302 acres. The applicant, Golden Fields Solar IV, LLC, is a Clearway Energy Group subsidiary.
Who owns the Rosamond South solar project?
County records name Golden Fields Solar IV, LLC as the applicant and describe it as a Clearway Energy Group subsidiary. Clearway built and operates the first phase, Rosamond South 1. The company says Global Infrastructure Partners and TotalEnergies own it, and that it holds about 13.6 GW of gross capacity in 27 states.
Is Rosamond South Solar operating?
Partly. Clearway said on Nov. 5, 2025, that Rosamond South 1, with 140 MW of solar and 117 MW of storage, was in commercial operation. The county approved more: 165 MW of solar and 245 MW of storage. Federal data lists a planned Rosamond South II battery, but its link to this entitlement is unconfirmed.
What did CDFW approve for Rosamond South in August 2026?
On Aug. 17, 2026, CDFW approved Amendment No. 4 to the western Joshua tree incidental take permit, No. 1927-ITP-2023-018-04. The amendment revises the tree preservation condition and extends the deadline to record a conservation easement. It leaves the project’s size and the 1,354-tree total unchanged. The agency filed notice Aug. 18.
How many Joshua trees does the Rosamond South project affect?
The permit now authorizes incidental take of 1,354 western Joshua trees. It began at 1,346 in February 2024. Amendment No. 1 added one tree, Amendment No. 2 brought the total to 1,371, and Amendment No. 3 added 229 and removed 246. Amendment No. 4 did not change the count.
Who buys the power from Rosamond South?
Clearway lists MCE, the University of California, Rancho Cucamonga Municipal Utility, Eastside Power Authority, the City of Moreno Valley and Constellation Energy as long-term buyers for Rosamond South 1. Solar Power World’s 2024 report described 15-year agreements with the first five. Clearway says the 140 MW solar and 117 MW storage complex can serve more than 72,000 homes a year.
If you own land near Rosamond or Willow Springs, or need yard and industrial space to support energy construction in East Kern, call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us to talk through values, leasing and what projects like Rosamond South mean for your property. Get Kern County CRE news monthly: subscribe to the Kern CRE report.
Sources
- Rosamond South Solar Project; Amendment No. 4 to the WJTCA Incidental Take Permit No. 1927-ITP-2023-018-04, Notice of Determination, SCH 2021060079, CEQAnet (Governor’s Office of Land Use and Climate Innovation), received Aug. 18, 2026.
- Notice of Determination, Rosamond South Solar Project ITP Amendment No. 4 (signed PDF), California Department of Fish and Wildlife, August 2026.
- Amendment No. 3 to WJTCA ITP No. 1927-ITP-2023-018-04, Notice of Determination, CEQAnet, July 2, 2025.
- Amendment No. 2 to WJTCA ITP No. 1927-ITP-2023-018-04, Notice of Determination, CEQAnet, March 26, 2025.
- Amendment No. 1 to WJTCA ITP No. 1927-ITP-2023-018-04, Notice of Determination, CEQAnet, Nov. 7, 2024.
- Rosamond South Solar Project (WJTCA Incidental Take Permit No. 1927-ITP-2023-018-04), Notice of Determination, CEQAnet, Feb. 23, 2024.
- Rosamond South Solar Project, Notice of Determination (Board of Supervisors approval Dec. 13, 2022), CEQAnet, received Dec. 15, 2022.
- Rosamond South Solar Project by Golden Fields Solar IV, LLC, Draft EIR, CEQAnet, received July 13, 2022.
- Notice of Preparation of a Draft EIR, Rosamond South Solar Project, Kern County Planning and Natural Resources Department, June 3, 2021.
- Comments on the Rosamond South Solar Project Draft EIR (SCH 2021060079), California Department of Fish and Wildlife, Aug. 30, 2022.
- Rosamond South Solar Project (EIR volumes, hearing dates and staff reports), Kern County Planning and Natural Resources Department.
- Clearway begins construction on latest solar + storage project in California, Solar Power World, Aug. 26, 2024.
- Clearway Brings Online Grid-Enhancing Rosamond South Energy Center in California, Clearway Energy Group, Nov. 5, 2025.
- Our team and values (About), Clearway Energy Group.
- Rosamond South 1 solar farm, Global Energy Monitor.
- Rosamond South II, EIA plant 69648, interconnection.fyi (EIA Form 860M data).
- Notice of Determination, Discovery Solar PV and Storage Project Incidental Take Permit (western Joshua tree candidate status), California Department of Fish and Wildlife, Sept. 28, 2026.
- Euismod Energy Storage Project, Draft EIR, SCH 2025120791, CEQAnet, received Aug. 6, 2026.
- Sen. Blakespear’s legislation to protect solar tax incentive signed by Governor (SB 710), Office of Sen. Catherine Blakespear, Oct. 6, 2025.
- Regional brokerage market reports (Bakersfield industrial, Q2 2026).
- Regional brokerage market reports (Bakersfield industrial, July 2026).
- Regional brokerage market reports (Feb. 26, 2026).
About this article
Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.