Solar Tax Credit 2026 Commercial Rules After the One Big Beautiful Bill: Deadlines for Kern County Projects and Landowners

Wind and solar credits now hinge on a July 4, 2026 construction start or a 2027 in-service date. A court threw out Treasury’s tighter test, and storage keeps its credit into the 2030s.

The solar tax credit 2026 commercial projects can still claim is the federal Section 48E investment credit or Section 45Y production credit. Under the One Big Beautiful Bill Act (OBBBA), signed July 4, 2025, solar that began construction by July 4, 2026 keeps the credit. Later starts must be in service by Dec. 31, 2027. Battery storage keeps full credits for projects that start construction through 2033. Kern County, California, developers and landowners face these deadlines now.

Solar and storage tax credits at a glance

ItemDetail
LawOne Big Beautiful Bill Act, H.R. 1, Public Law 119-21
SignedJuly 4, 2025
Credits affectedSection 48E clean electricity investment credit and Section 45Y production credit; Section 25D residential credit ended after 2025
Solar and wind deadlineBegin construction by July 4, 2026, or be placed in service by Dec. 31, 2027
Energy storageFull credit for construction starting through 2033; 75% in 2034, 50% in 2035, none from 2036
Foreign entity rulesMaterial assistance limits for construction starting after Dec. 31, 2025
Administered byInternal Revenue Service and U.S. Treasury Department
StatusIn effect. A federal court vacated IRS Notice 2025-42 on June 6, 2026; no appeal has been reported
California angleProperty tax exclusion for solar applies to systems installed before Jan. 1, 2027

Key takeaways

  • A solar facility that began construction after July 4, 2026 must be placed in service by Dec. 31, 2027 to claim the Section 48E or 45Y credit.
  • On June 6, 2026, a federal court in Oregon Environmental Council v. IRS (D.D.C. No. 25-4400) vacated IRS Notice 2025-42 and restored the 5% cost safe harbor for starting construction. An appeal could change that.
  • Energy storage keeps the full credit for projects that begin construction through 2033. It drops to 75% in 2034, 50% in 2035 and zero from 2036.
  • For projects that begin construction in 2026, solar facilities need a 40% non-prohibited-foreign-entity cost share and storage needs 55%. Both thresholds rise each year.
  • California’s property tax exclusion covers solar systems installed before Jan. 1, 2027. SB 710 (2025) lets those owners keep it until the property changes hands.

What is the commercial solar tax credit, and what did the One Big Beautiful Bill change?

Commercial solar and storage claim the Section 48E investment credit or the Section 45Y production credit, both created by the Inflation Reduction Act. The OBBBA put an end date on wind and solar but left storage alone.

The 48E credit is 30% of eligible cost for projects that meet prevailing wage and apprenticeship rules. Ten-point bonuses apply for domestic content and for sites in energy communities. The credit can be sold to another taxpayer or, for some entities, received as a direct payment, according to the IRS.

The OBBBA (H.R. 1, Public Law 119-21) says a facility that begins construction after July 4, 2026 must be placed in service by Dec. 31, 2027 to qualify, according to The Tax Adviser and Kirkland & Ellis. Projects that began on or before July 4, 2026 escape the 2027 cutoff, though they must keep building continuously.

The law also ended the residential Section 25D credit for expenditures after Dec. 31, 2025, per the IRS. That affects homeowners. Commercial buildings use 48E.

What are the solar tax credit 2026 commercial deadlines?

Solar and wind face a hard calendar, while storage has a long runway. The table lays out each date.

Project typeKey dateRule
Solar or wind, construction began by July 4, 2026Continuity ruleKeeps the credit if construction continues; IRS guidance has used a four-calendar-year continuity safe harbor
Solar or wind, construction began after July 4, 2026Dec. 31, 2027Must be placed in service by this date or no credit
Energy storage, construction begins 2026 to 2033No near-term cutoffFull credit, subject to foreign entity rules
Energy storage, construction begins 2034203475% of the credit
Energy storage, construction begins 2035203550% of the credit
Energy storage, construction begins 2036 or later2036No credit
Any claimant that is a prohibited foreign entityTax years beginning after July 4, 2025No credit
Residential solar (Section 25D)Dec. 31, 2025No credit for expenditures after this date

Sources: The Tax Adviser (solar deadlines, continuity rule and foreign entity dates); Kirkland & Ellis (storage phase-down); IRS (Section 25D).

Storage was not part of the wind and solar cutoff, The Tax Adviser notes. That is why standalone batteries keep a much longer runway. For the storage side of the rules, see our guide to battery energy storage regulations in California.

How do you prove construction began, and what happened to Notice 2025-42?

Because July 4, 2026 is a construction-start test, the method of proof matters. IRS guidance has long allowed two: starting physical work of a significant nature, or paying or incurring at least 5% of a project’s total cost (the 5% safe harbor).

Treasury tightened that on Aug. 15, 2025. Notice 2025-42 limited wind and solar projects that began construction on or after Sept. 2, 2025 to the physical work test. It kept the 5% safe harbor only for solar facilities of 1.5 megawatts or less of net output, according to The Tax Adviser.

Then a court stepped in. On June 6, 2026, the U.S. District Court for the District of Columbia ruled in Oregon Environmental Council v. IRS (No. 25-4400) that the notice violated the Administrative Procedure Act. It vacated the notice nationwide and restored the 5% safe harbor for wind and solar, McGuireWoods reported. Kean Miller urged developers to keep records supporting both tests. PwC said the decision could still be stayed, modified or reversed on appeal.

No appeal, stay or replacement IRS guidance has been reported. A reversal on appeal would reopen the question of which test applies.

Why the ruling matters in Kern County

A project that paid 5% of its costs before July 4, 2026 but did little physical work may now qualify, as long as the ruling stands. A project that relied only on spending is exposed if an appeals court reverses. For anyone buying land under a solar option, lending on a project or buying transferred credits, the test the developer used and the documentation behind it determine how exposed the credit is.

What are the foreign entity of concern rules?

The OBBBA added two layers of foreign-entity limits. One applies to the taxpayer. The other applies to the project’s supply chain.

First, a taxpayer that is itself a prohibited foreign entity cannot claim 48E or 45Y for tax years beginning after July 4, 2025. An entity owned at least 25% by one is also treated as restricted, per The Tax Adviser. Credits also cannot be transferred to a specified foreign entity.

Second, for facilities that begin construction after Dec. 31, 2025, the credit is lost if the project includes too much material assistance from prohibited foreign entities. The test is a cost ratio. Kirkland & Ellis reported that at least 40% of a solar facility’s manufactured product costs must come from non-prohibited sources for 2026 starts, rising to 60% for 2030 and later. For storage the threshold starts at 55% and rises to 75%.

Treasury has since issued interim guidance. IRS Notice 2026-15, issued March 20, 2026, explains how to calculate the ratio, including safe harbor tables and reliance on supplier certifications, according to Nixon Peabody. Because many batteries and solar components trace to Chinese supply chains, these thresholds are a procurement problem as much as a tax one.

How do the deadlines affect Kern County solar and storage projects?

Any Kern solar project with an in-service date after 2027 needs a construction start by July 4, 2026 to keep the federal credit. The storage half of a hybrid project is treated separately and keeps its credit much longer.

Kern County approved several large projects in 2026. The Kern County Board of Supervisors approved Terra-Gen’s Discovery project, up to 1,400 megawatts of solar and 8 gigawatt-hours of storage, on June 16, 2026. Terra-Gen projects about $44 million in property tax revenue in the first full year of operation, according to 23ABC News. Supervisors approved Terra-Gen’s Galaxy project, up to 600 megawatts of solar and 4 gigawatt-hours of storage near Mojave, on Sept. 29, 2026, PV Tech reported.

Clearway’s Rosamond South 1, with 140 megawatts of solar and 117 megawatts of storage, reached commercial operation in November 2025, the company said. On the small end, Kern County approved a 1,477-kilowatt accessory array for an industrial user near Mojave in July 2026, according to CEQAnet. Our MAG Energy solar article covers that project. Expect more storage-heavy designs and standalone battery proposals in East Kern.

What does it mean for Kern landowners and commercial property owners?

The answer depends on whether you own land under a solar option, a warehouse roof or an interest in a credit transaction.

Farmland and desert landowners with solar options

Many Kern solar leases sit on land where groundwater limits under the Sustainable Groundwater Management Act have made fallowing more likely. A developer that missed the July 4, 2026 start may not finish by the end of 2027, and without the credit some projects will not pencil. Expect renegotiated options, longer extension requests or terminations. Extension fees, termination rights and restoration duties in the option decide who carries that risk.

Warehouse and industrial owners considering rooftop or carport solar

An owner that did not start construction by July 4, 2026 needs a system in service by Dec. 31, 2027 to claim 48E. That is achievable for many rooftop projects, but utility interconnection and equipment lead times can eat the margin. Batteries added to a building keep their credit longer than the panels. Our NEM 3.0 commercial solar guide covers how system size interacts with export credits.

Buyers, lenders and credit purchasers

Buyers and lenders typically want construction-start evidence, the foreign entity cost analysis, prevailing wage records and the in-service schedule. A credit that fails can be recaptured or disallowed, so indemnities in transfer agreements matter. Our One Big Beautiful Bill Act real estate guide covers the wider changes for owners and investors.

What happens to California’s solar property tax exclusion?

California excludes active solar energy systems from reassessment as new construction (Revenue and Taxation Code section 73). Under SB 710 (Blakespear, 2025), systems installed before Jan. 1, 2027 keep the exclusion until the property sells, Sen. Catherine Blakespear’s office said.

A 2026 bill to extend the exclusion for customer-sited systems, AB 2389, was held under submission in committee on May 14, 2026, according to LegiScan. The Legislature’s 2026 session ended Aug. 31, and the bill did not advance after that. Unless new law passes, solar installed in 2027 or later would likely be assessed like other new construction. For a building owner, that is a second reason to finish in 2026. For Kern County’s tax base, it means future solar adds to the rolls.

What to watch and a practical checklist

  • Appeal of the Notice 2025-42 ruling: a reversal could undercut projects that relied on the 5% safe harbor.
  • Dec. 31, 2027: in-service deadline for solar that began construction after July 4, 2026.
  • Jan. 1, 2027: California’s solar property tax exclusion ends for new installations unless extended.
  • Treasury foreign entity guidance: further rules on the material assistance calculation could affect storage procurement.
  • 2034: storage credits begin to phase down for new construction starts.
  • Checklist: a project file typically documents the construction start under both tests, the in-service schedule and interconnection date, the foreign entity cost ratio, prevailing wage compliance and the site’s energy community status. A CPA can model the credit before an owner relies on it.

Worked example: a rooftop solar and battery system on a Bakersfield warehouse

Assume an owner installs a $2,000,000 rooftop solar array and a $600,000 battery on a Bakersfield warehouse. The owner meets prevailing wage and apprenticeship rules where they apply and qualifies for no bonus credits. These figures are illustrative, not quotes or tax advice.

Missing the 2027 in-service date costs the solar credit entirely, while the battery credit survives. Domestic content or energy community bonuses, foreign entity limits and basis rules would change the numbers.

ScenarioSolar credit (30% of $2.0M)Battery credit (30% of $600K)Total
Construction began by July 4, 2026$600,000$180,000$780,000
Construction began after July 4, 2026; in service by Dec. 31, 2027$600,000$180,000$780,000
Construction began after July 4, 2026; in service in 2028$0$180,000$180,000

Frequently asked questions

Is there still a commercial solar tax credit in 2026?

Yes. Commercial solar can claim the Section 48E investment credit or the 45Y production credit, generally 30% with prevailing wage and apprenticeship compliance. A solar facility that began construction by July 4, 2026 keeps eligibility. One that began later must be in service by Dec. 31, 2027. Foreign entity limits also apply to projects that start construction after 2025.

What does “begin construction” mean for the solar credit?

IRS guidance recognizes two methods: starting physical work of a significant nature, or paying or incurring at least 5% of total project cost. Notice 2025-42 limited most solar to the physical work test for starts on or after Sept. 2, 2025. A federal court vacated that notice on June 6, 2026, which restores the 5% option unless an appeal reverses it. Keep records for both tests.

Do battery storage projects lose the tax credit in 2027?

No. The July 4, 2026 and Dec. 31, 2027 deadlines apply to wind and solar only. Storage keeps the full credit for projects that begin construction through 2033, then 75% for 2034 starts, 50% for 2035 and nothing from 2036. Storage projects that start after 2025 must still pass the foreign entity cost test, which begins at 55%.

Can I still claim the residential solar tax credit?

Not for new spending. The OBBBA ended the Section 25D residential credit for expenditures after Dec. 31, 2025. Homeowners who paid for systems in 2025 or earlier may still claim it on returns for those years. Businesses with solar on commercial or industrial property use the 48E or 45Y credits and follow the commercial deadlines.

What are the foreign entity of concern rules for solar?

A taxpayer that is a prohibited foreign entity cannot claim 48E or 45Y for tax years beginning after July 4, 2025. For facilities that begin construction after Dec. 31, 2025, the credit is denied if too much manufactured product cost comes from prohibited foreign entities. The non-prohibited share must be at least 40% for solar and 55% for storage in 2026, and it rises each year.

Will new solar in California pay property tax after 2026?

Likely, unless the law changes. The new-construction exclusion for active solar covers systems installed before Jan. 1, 2027, and SB 710 lets those owners keep it until a sale. AB 2389, which would have extended the exclusion for customer-sited systems, was held in committee in May 2026.

Should a Kern landowner worry about an existing solar option?

It can be. Projects that did not begin construction by July 4, 2026 must be in service by the end of 2027 to keep the federal credit, and some may stall. The option’s term, extension payments, termination rights and restoration duties decide what a landowner gets if a developer stalls. How the developer documented its construction start also matters.

If you own land under a solar option, are weighing a storage lease or are thinking about rooftop solar on a Kern County building, Kern CRE can help you work through the real estate side of the decision. Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us. Get Kern County CRE news monthly: subscribe to the Kern CRE report.

Sources

  1. Navigating safe-harbor rules for solar and wind Sec. 48E facilities, The Tax Adviser (AICPA), Lynn Mucenski-Keck, Feb. 10, 2026.
  2. Federal Court Vacates IRS Notice 2025-42, Restores 5% Safe Harbor for Wind and Solar Projects, McGuireWoods, June 8, 2026.
  3. Court Vacates IRS Notice 2025-42: What It Means for Solar and Wind Energy Tax Credits, Kean Miller, June 10, 2026.
  4. Invalidated IRS Notice 2025-42 creates uncertainty, PwC, June 2026.
  5. One Big Beautiful Bill Act Brings Big Changes to Green Energy Tax Credits, Kirkland & Ellis, Aug. 6, 2025.
  6. Foreign Entities of Concern, the Material Assistance Rule and IRS Notice 2026-15, Nixon Peabody, March 20, 2026.
  7. One, Big, Beautiful Bill provisions, Internal Revenue Service.
  8. Clean Electricity Investment Credit, Internal Revenue Service.
  9. H.R. 1, One Big Beautiful Bill Act (119th Congress), Congress.gov, enacted July 4, 2025.
  10. Sen. Blakespear’s legislation to protect solar tax incentive signed by Governor, Office of Sen. Catherine Blakespear, Oct. 6, 2025.
  11. California AB 2389, Property taxation: active solar energy systems: customer sited: extension, LegiScan.
  12. Kern County approves Discovery Solar project amid revenue concerns, 23ABC News (KERO), Ruby Rivera, June 19, 2026.
  13. Kern County approves 600MW/4GWh solar-plus-storage project from Terra-Gen in California, PV Tech, Sept. 30, 2026.
  14. Clearway Brings Online Grid-Enhancing Rosamond South Energy Center in California, Clearway Energy Group, Nov. 5, 2025.
  15. MAG Energy accessory solar, Notice of Exemption, SCH 2026070647, CEQAnet (State Clearinghouse), July 16, 2026.

About this article

Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. It is general information, not legal, tax, investment or financial advice; talk with a qualified professional about your situation.