What Kern County and the state approved for Terra-Gen on 7,700 acres between Mojave and Tehachapi, what the new wildlife permit covers, and what a projected $44 million first-year tax bill means for East Kern.
The Discovery Solar project Kern County supervisors approved on June 16, 2026, is Terra-Gen’s plan for up to 1,400 megawatts (MW) of solar and up to 8 gigawatt-hours (GWh) of battery storage. It spans about 7,700 acres and 473 private parcels, roughly 6 miles southwest of Mojave. On Sept. 28, 2026, the California Department of Fish and Wildlife (CDFW) approved its state incidental take permit, and the state logged the notice Sept. 29.
Key takeaways
- The Kern County Board of Supervisors approved the Discovery Solar PV and Storage Project on June 16, 2026, on a 3-to-1 vote, according to 23ABC and KUZZ.
- The approvals cover up to 1,400 MW of solar and up to 8 GWh of battery storage (about 1,000 MW of storage equipment) on about 7,700 acres across 473 privately owned parcels, with a gen-tie line to the existing Windhub Substation.
- CDFW approved Incidental Take Permit No. 2081(b)-2026-008-04 on Sept. 28, 2026. It covers Bakersfield cactus, western Joshua tree, western burrowing owl and LeConte’s thrasher.
- Terra-Gen projects about $44 million in property tax revenue in the first full year of operation. KUZZ reported more than $750 million in tax revenue over a 35-year life.
- Construction is expected to average about 470 workers a day and peak near 660. KUZZ reported that operations are expected to begin by late 2029.
Discovery Solar at a glance
| Item | Detail |
|---|---|
| Project | Discovery Solar PV and Storage Project (State Clearinghouse No. 2025071048) |
| Location | South of State Route 58 and west of State Route 14, on both sides of Tehachapi Willow Springs Road; about 6 miles southwest of Mojave, 9 miles southeast of Tehachapi and 8 miles northwest of Rosamond (unincorporated southeast Kern County) |
| Applicant/owner | Discovery Solar PV and Storage, LLC, a Terra-Gen project company |
| Jurisdiction | Kern County (lead agency: Planning and Natural Resources Department and Board of Supervisors); California Department of Fish and Wildlife (state take permit) |
| Case numbers | CDFW Incidental Take Permit No. 2081(b)-2026-008-04; county approvals include four zone changes (Maps 197, 198, 214 and 215), five conditional use permits, four general plan amendments, four zone variances and 15 vesting tentative parcel maps |
| Parcels | 473 privately owned parcels (first APN listed: 474-060-17) |
| Size | About 7,700 acres; up to 1,400 MW solar; up to 8 GWh storage (about 1,000 MW) |
| Use | Utility-scale solar and battery storage with an operations and maintenance facility, a 230-kV switchyard, up to three collector substations, temporary laydown yards and a gen-tie line to Windhub Substation |
| Status | Approved by the Board of Supervisors June 16, 2026 (EIR certified with a Statement of Overriding Considerations; county notice received June 18); CDFW take permit approved Sept. 28, notice received Sept. 29 |
| Next step | CEQA challenge window on CDFW’s notice; county construction permits; about 34 months of construction, with operations expected by late 2029 per KUZZ |
What is the Discovery Solar project in Kern County?
Discovery Solar PV and Storage is a utility-scale solar and battery project from Discovery Solar PV and Storage, LLC, a Terra-Gen project company. The county’s Notice of Determination describes up to 1,400 MW of photovoltaic generation with up to 8 GWh of storage on about 7,700 acres of unincorporated southeast Kern County.
The Kern County Board of Supervisors certified the environmental impact report (EIR) and approved the land-use entitlements on June 16, 2026. 23ABC reported a 3-to-1 vote, and KUZZ reported the same count. The county’s meeting recap confirms the approval but does not give the tally. The Planning Commission heard the project first, on April 23, 2026, according to the county’s project page, and voted to approve staff’s recommendations and send the project to supervisors.
Supervisors adopted findings, a mitigation monitoring program and a Statement of Overriding Considerations. That last step means the EIR identified significant effects that could not be fully avoided, and the board approved the project anyway because of its benefits. For background on how county land-use approvals work, see our guide to the industrial land entitlement process and CEQA in Kern County.
What gets built?
The Final EIR filing lists the solar arrays, an operations and maintenance facility, telecommunications equipment, the energy storage system, a 230-kilovolt switchyard, up to three onsite collector substations and temporary construction laydown yards. A generation-tie line would carry power to the existing Windhub Substation, which Energy-Storage.News identified as a Southern California Edison facility.
The storage is the standout number. State filings put the 8 GWh at about 1,000 MW of equipment, or roughly eight hours of discharge at full output. By our calculation, that is more than twice the 3,287 MWh at Terra-Gen’s own Edwards Sanborn complex, which Energy-Storage.News called the world’s largest battery site when it came fully online in 2024. Terra-Gen says Discovery will use U.S.-manufactured panels by First Solar. For other East Kern storage proposals, see our report on the Euismod Energy Storage Project near Rosamond.
What does the entitlement package include?
Because the site is a patchwork of small lots, the approvals are extensive. They include:
- Four zone changes, on zoning Maps 197, 198, 214 and 215, that move agricultural and residential land into exclusive agriculture zoning.
- Five conditional use permits for solar facilities ranging from 150 MW to 550 MW.
- Four zone variances for parcels of about 2.5 to 19.9 gross acres where the zone requires 20 gross acres.
- Four general plan amendments that remove future road reservations along section and mid-section lines.
- Fifteen vesting tentative parcel maps that merge between 4 and 68 lots at a time into parcels of about 20 to 522 acres.
What does the Discovery Solar take permit cover?
The permit covers take of one state endangered plant and three state candidate species. On Sept. 28, 2026, CDFW approved Incidental Take Permit No. 2081(b)-2026-008-04 under the California Endangered Species Act. The State Clearinghouse received CDFW’s Notice of Determination the next day.
The signed notice lists the state endangered Bakersfield cactus and three state candidates for listing: the western Joshua tree, the western burrowing owl and LeConte’s thrasher. CDFW acted as a responsible agency, relied on the county’s certified EIR and made mitigation measures a condition of its approval. The notice does not list the permit’s acreage, compensation lands or term. Those details sit in the permit itself.
What did CDFW flag during review?
CDFW’s March 13, 2026 comment letter on the Draft EIR describes a desert site between 2,970 and 3,760 feet in elevation, with creosote bush scrub on about 66% of the land and Joshua tree woodland among its plant communities. The letter said LeConte’s thrasher was documented on the site.
On cactus, the letter said the botanical survey did not report Bakersfield cactus but did identify hundreds of beavertail cactus, a related variety. CDFW recommended a state take permit if take of the endangered cactus could not be avoided.
Joshua trees raise the larger logistics question. CDFW pointed to a Draft EIR measure calling for relocation of “a minimum of 10,000 onsite WJT stems” to a 50-foot vegetated strip (WJT is western Joshua tree). It questioned whether moving that many is feasible, noting the number is far higher than known relocation efforts on other projects. The final mitigation measure may differ from the draft.
Where is the Discovery Solar site, and what was there before?
The site sits near the unincorporated communities of Mojave and Rosamond, south of State Route 58 and west of Highway 14, on both sides of Tehachapi Willow Springs Road. The state CEQA listing puts it on the western edge of the Antelope Valley, about 6 miles southwest of Mojave, 9 miles southeast of Tehachapi, 8 miles northwest of Rosamond and 20 miles west of Edwards Air Force Base.
Nearby features in that record include SR 58, the Union Pacific line, the Los Angeles Department of Water and Power aqueduct, the future California high-speed rail route and the Mojave Air and Space Port. Power will leave through Windhub Substation, the same connection point as Terra-Gen’s Galaxy Solar project.
How do 473 parcels become one site?
This is an assemblage, not a single ranch. The notice counts 473 privately owned parcels, an average of about 16 acres each (7,700 acres divided by 473, our arithmetic). Many fall below the 20-acre zoning minimum, which is why the county approved variances. The general plan amendments drop future road reservations mapped along section lines, and the 15 parcel maps then merge lots into blocks large enough to build on.
The zone changes show the starting point: agricultural and residential zoning across four county maps. On the ground, CDFW describes Mojave desert scrub and Joshua tree woodland.
How does Discovery fit with Galaxy Solar?
Discovery is not Terra-Gen’s only East Kern approval this year. Supervisors approved the Galaxy Solar project, up to 600 MW and 4 GWh on about 3,519 acres southeast of Mojave, on Sept. 29, 2026. Together, by our arithmetic, the two total about 2,000 MW of solar and 12 GWh of storage on roughly 11,200 acres, both tied to Windhub.
Who is behind Discovery Solar?
Terra-Gen is an independent power producer owned by Masdar, the United Arab Emirates government-owned clean energy company, and Igneo Infrastructure Partners. Masdar closed its purchase of Energy Capital Partners’ 50% stake in October 2024, PV Tech reported. At a June 3 meeting of the Greater Tehachapi Economic Development Council, a Terra-Gen environmental planning executive presented the project, The Loop reported.
The company says it operates 4.2 GW of wind, solar and battery projects with 5.6 GWh of storage. Kern County is central to its business. Terra-Gen’s project list shows five operating Kern solar projects totaling 1,325 MW, including Edwards Sanborn, and the 368 MW EdSan 2 under construction.
What does Discovery Solar mean for Kern County’s tax base and real estate?
Discovery would add a large tax base but no leasable buildings. The sections below separate the tax projections from the land and industrial-market effects.
A projected $44 million first-year property tax bill
Terra-Gen’s project page projects about $44 million in property tax revenue in the first full year of operation, plus sales tax and other local benefits. The Loop reported $205 million in property tax revenue expected over the first five years, and KUZZ reported more than $750 million in tax revenue over a 35-year life. These are projections from the company and news reports.
Timing matters to the size of the bill. California’s property tax exclusion for new active solar energy systems covers systems installed by the end of 2026, and SB 710 lets those systems keep the break until the property sells, according to Sen. Catherine Blakespear’s office. A plant expected to begin operating in late 2029, as KUZZ reported, would fall after that deadline unless the Legislature extends it. For the federal side of solar economics, see our guide to the commercial solar tax credit.
Land: the value is in the assembly
The county record shows the pattern: 473 small private parcels, many under the zoning minimum, combined into one site with a transmission connection.
Industrial space, contractors and power
A national brokerage’s Q2 2026 Bakersfield industrial report put availability at 10.1%, with asking rent averaging $0.71 per square foot per month, triple net, and one building of about 510,000 square feet in Arvin under construction. A regional brokerage report measured Q2 2026 vacancy at 9.55%. Neither report breaks out Mojave or Tehachapi.
Discovery adds no leasable buildings. 23ABC reported that construction will employ an average of 470 workers a day and reach about 660 at peak, and Terra-Gen expects about 34 months of construction, per Energy-Storage.News.
The storage also matters beyond the fence line. The California Energy Commission said the state passed 21,000 MW of battery resources in August 2026, so Discovery’s roughly 1,000 MW would equal about 5% of that fleet. In a Feb. 26, 2026 release, a national brokerage said power availability, reliability and costs “are increasingly shaping site selection, development feasibility and asset performance.” For industrial users who rank power first, East Kern’s growing generation and storage base is part of the region’s pitch. For the rules that govern such projects, see our overview of battery energy storage regulations in California.
What concerns and support came up?
The main concern at the hearing was fiscal, and local business groups backed the project. Supervisor Phillip Peters questioned the trade at the June 16 hearing. “I’m not opposed to renewable energy, but I do believe we have a responsibility to ask the question, what are Kern County residents receiving in return?” he said, 23ABC reported. Citing state tax exemptions for renewable energy projects, he questioned how much revenue stays local for roads, public safety and schools.
Peters added: “California continues to talk to Kern County about a just transition, but the reality is the rest of the state gets to transition to green energy, while Kern County just gets to host the projects.”
Claire Scotty, executive director of the Greater Tehachapi Chamber of Commerce, called the project “a meaningful and forward-looking investment in East Kern County’s economy,” per 23ABC. The Greater Tehachapi Economic Development Council voted unanimously to send supervisors a letter of support. No organized opposition or court challenge had been reported beyond those fiscal questions and CDFW’s comments.
What happens next for the Discovery Solar project?
The next milestones are a CEQA challenge window, county construction permits and the grid interconnection. CDFW’s Sept. 29 notice opens a challenge period for the permit, generally 30 days from the filing, which would run to about Oct. 29. No lawsuit had been reported. Terra-Gen still needs county construction-level permits and must complete its grid interconnection.
Terra-Gen expects construction to take about 34 months and to begin after it receives all permits and agency approvals, Energy-Storage.News reported. KUZZ reported that operations are expected to begin by late 2029. Terra-Gen had not announced power buyers or a construction start date.
A power purchase or storage contract, grading permits and contractor mobilization near Tehachapi Willow Springs Road would signal that construction is close.
Frequently asked questions
What is the Discovery Solar project in Kern County?
It is a Terra-Gen development approved for up to 1,400 megawatts of solar generation and up to 8 gigawatt-hours of battery storage. The project covers about 7,700 acres across 473 private parcels southwest of Mojave in unincorporated Kern County. The Kern County Board of Supervisors approved it on June 16, 2026.
Where is the Discovery Solar site?
The site lies south of State Route 58 and west of Highway 14, on both sides of Tehachapi Willow Springs Road. State records place it about 6 miles southwest of Mojave and 9 miles southeast of Tehachapi, on the western edge of the Antelope Valley. Power will connect to the existing Windhub Substation.
What did the state’s incidental take permit approve?
The California Department of Fish and Wildlife issued a permit under the California Endangered Species Act on Sept. 28, 2026. It allows incidental take of the endangered Bakersfield cactus and three candidate species: the western Joshua tree, western burrowing owl and LeConte’s thrasher. The permit’s acreage, mitigation lands and term are not in the public notice.
How much property tax will Discovery Solar pay?
Terra-Gen projects about $44 million in the first full year of operation. News reports cite $205 million over five years and more than $750 million over 35 years. These are projections, and the solar property tax exclusion currently ends for systems installed after 2026, which is before the plant is expected to operate.
How many jobs will Discovery Solar create?
23ABC reported that construction will average 470 workers a day and peak near 660. The Loop reported more than 650 union construction jobs, and Terra-Gen’s project page says over 600. No confirmed count of permanent operating jobs had been published, and solar plants typically need far fewer workers once running.
When will Discovery Solar be built?
Terra-Gen expects about 34 months of construction once all permits and approvals are in hand. KUZZ reported that operations should begin by late 2029. No construction start date or power buyer had been announced.
How is Discovery Solar related to the Galaxy Solar project?
Both are Terra-Gen solar and storage projects in East Kern that connect to the Windhub Substation. Galaxy covers up to 600 MW and 4 GWh on about 3,519 acres southeast of Mojave. Discovery is more than twice as large, at 1,400 MW and 8 GWh on about 7,700 acres.
Own land near Mojave, Rosamond or Tehachapi, or weighing how a project this size affects nearby values, yards or leasing? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us. Get Kern County CRE news monthly: subscribe to the Kern CRE report.
Sources
- CEQAnet, Discovery Solar PV and Storage Project, CESA Incidental Take Permit No. 2081(b)-2026-008-04, Notice of Determination (SCH 2025071048), Governor’s Office of Land Use and Climate Innovation, received Sept. 29, 2026.
- California Department of Fish and Wildlife, Notice of Determination, Discovery Solar PV and Storage Project Incidental Take Permit (signed PDF), CDFW, Sept. 28, 2026.
- CEQAnet, Discovery Solar PV and Storage Project, Notice of Determination (Board of Supervisors approval), received June 18, 2026.
- CEQAnet, Discovery Solar PV and Storage Project, Response to Comments (Final EIR), received April 8, 2026.
- CEQAnet, Discovery Solar PV and Storage Project, Draft EIR, received Jan. 22, 2026.
- CEQAnet, Discovery Solar PV and Storage Project, Notice of Preparation, received July 24, 2025.
- California Department of Fish and Wildlife, Comments on the Draft EIR, Discovery Solar PV and Storage Project (SCH 2025071048), CDFW, March 13, 2026.
- Kern County Planning and Natural Resources Department, Discovery Solar PV and Storage Project (EIR volumes, hearing dates and staff reports).
- County of Kern, Board of Supervisors Meeting Recap for June 16, 2026, June 2026.
- Citizen Portal, Kern County planning panel backs 1,400-MW Discovery solar and storage project, forwards it to supervisors, April 23, 2026.
- 23ABC News, Kern County approves Discovery Solar project amid revenue concerns, June 19, 2026.
- KUZZ News, Supervisors Approve Mojave Solar Facility, June 17, 2026.
- The Loop Newspaper, GTEDC pledges support for Terra-Gen Solar Project, June 20, 2026.
- Terra-Gen, Discovery Solar Storage (project page).
- SolarBytes, Terra-Gen wins approval for 1.4 GW California solar project, June 29, 2026.
- Energy-Storage.News, Officials in Kern County, California, begin permitting process for Terra-Gen’s 8GWh LDES BESS, July 31, 2025.
- Energy-Storage.News, California solar-plus-storage project with world’s largest BESS fully online, Jan. 24, 2024.
- PV Tech, Masdar closes acquisition of US IPP Terra-Gen, Oct. 2, 2024.
- Terra-Gen, Our Story.
- Terra-Gen, Solar Energy (project list).
- Office of Sen. Catherine Blakespear, Sen. Blakespear’s legislation to protect solar tax incentive signed by Governor (SB 710), Oct. 6, 2025.
- Regional brokerage market reports (Bakersfield industrial, Q2 2026).
- Regional brokerage market reports (Bakersfield industrial, July 2026).
- California Energy Commission, California surpasses 21,000 megawatts of battery resources supporting the state’s electric grid, August 2026.
- Regional brokerage market reports (Feb. 26, 2026).
About this article
Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.