Bakersfield Solar and Battery Project Approved for City Water Site at Up to $7.99 Million

The City Council approved the energy contract Oct. 7 after staff cut $1.2 million from an earlier version. Water rates already set will pay for it, and staff wants the solar running by the end of 2027 to keep a federal tax credit.

The Bakersfield City Council approved a solar and battery project for the city’s water site at 1000 Buena Vista Road on Oct. 7, 2026. The energy contract with Willdan Energy Solutions is capped at $7,990,188 and comes from the water fund, not the general fund. City staff projected about $382,000 in first-year electricity savings.

Key takeaways

  • The council approved the contract Oct. 7 with Council Members Eric Arias, Ken Weir and Zack Bashirtash absent. The mayor announced the motion approved without reading a tally.
  • The guaranteed maximum price of $7,990,188 covers carport solar panels, a battery system, parking lot upgrades, a city contingency and construction allowances.
  • Staff removed electric vehicle chargers and related site work from an earlier version, cutting the first cost by $1.2 million.
  • The water enterprise fund pays through a capital program already built into the city’s 2025 water rate study. Staff asked for no new money.
  • Staff projected nearly $10.4 million in savings from 2027 through 2041, with a 9.5-year payback if the solar is running by Dec. 31, 2027.
  • City Manager Christian Clegg called it the first of several energy projects the city expects to bring forward with the same firm.

Bakersfield water-site solar project at a glance

ItemDetail
ApprovedOct. 7, 2026, Bakersfield City Council (public hearing item 8B)
ContractorWilldan Energy Solutions, under an energy savings performance contract
Contract cap$7,990,188, guaranteed maximum price
SiteCity water site, 1000 Buena Vista Road, southwest Bakersfield
ScopeCarport solar panels, a battery system and parking lot upgrades
Paid byWater enterprise fund capital program (not the general fund)
Projected savingsAbout $382,000 in year one; nearly $10.4 million from 2027 through 2041 (city staff)
Payback9.5 years if energized by Dec. 31, 2027; 14.6 years if not (city staff)
IncentivesAbout $3.5 million, which staff described as federal tax credits

What does the Bakersfield solar and battery project include?

The project pairs a solar system built on carports over the site’s parking area with a battery system. The council approved a resolution authorizing an energy savings performance contract with Willdan Energy Solutions, not to exceed $7,990,188, for work at the Water Department site. The price also covers parking lot upgrades, a city contingency and construction allowances.

Water Director Daniel Maldonado told the council the site is one of the city’s largest tank sites. It runs a booster pump station around the clock and treats water from wells on the west side of the city, which explains its large power bill.

The contract uses a guaranteed maximum price. “This is the maximum price for the city unless the change orders are specifically requested by the city themselves,” Maldonado said. Any contingency the project does not use goes back to the water enterprise fund.

Who pays for the Bakersfield water-site solar project?

Water customers pay, through money already planned. Staff said the project sits in the water enterprise fund’s capital program, which was part of the city’s 2025 supplemental water rate study and Prop 218 rate process, and that no additional money was requested. Clegg confirmed it does not use the general fund.

Staff estimated the site’s electricity bill at about $682,000 in 2027, growing to more than $2 million by 2041 if rates rise 8% a year. Staff said rates have risen an average of 11.7% a year over the last five years and 8.2% a year over 15 years.

Why does the Dec. 31, 2027 deadline matter?

About $2 million of the incentives depends on energizing the solar by Dec. 31, 2027. Staff put the best-case net cost to the department at $4.4 million after about $3.5 million in incentives. About $1.5 million is already secured for the battery, and almost $2 million more is available for the solar. Miss the date and the payback stretches from 9.5 years to 14.6 years.

“If we don’t construct this project … we’ll miss out on $3.5 million in federal tax credits,” Maldonado said.

The date matches the 2025 federal budget law, H.R. 1. Under it, solar projects that did not begin construction by July 4, 2026 must be placed in service by Dec. 31, 2027 to claim the clean electricity investment credit, while battery storage kept its credit, according to a law firm summary of the act. Staff did not cite the law by name at the hearing. Kern CRE’s commercial solar tax credit guide covers the rules for private owners.

Why did the project come back to the council?

The council turned down an earlier version on Aug. 5, 2026, with a total cost of about $9.2 million, according to a Govly summary of that meeting. For the Oct. 7 hearing, staff dropped the EV chargers and related site work, which cut the first cost by $1.2 million.

Clegg said staff brought it back quickly “because there’s risk of losing important grant funds tax credits.” Council Member Larry Koman, whose Ward 5 includes the site, recalled opposing the project the first time over a payback of almost 18 years. “We’re down to somewhere between nine and 14 years,” Koman said before moving to approve it. No one spoke for or against the item during the public hearing.

What happens next?

The city can now sign the contract and start design and construction, with staff aiming to energize the solar by Dec. 31, 2027. Clegg said Willdan won a competitive request for proposals several years ago to develop energy projects with the city and that “this is actually the first of many projects to come forward.” No other projects were named.

What does the Bakersfield solar and battery project mean for property owners?

The city’s math is the same math many Kern County building owners run. A site with steady daytime load and a large parking lot can carry carport solar, and a battery shifts some of that power into evening hours when utility rates run higher. Staff’s rate assumptions, 8% a year with recent years running higher, show why owners of warehouses, cold storage and manufacturing buildings keep asking about on-site power.

The same federal calendar applies to private projects. A solar system that did not begin construction by July 4, 2026 has to be in service by the end of 2027 to claim the credit, which leaves about 14 months. Storage projects are not tied to that date. Kern CRE’s guides to commercial solar economics under NEM 3.0 and battery storage regulations in California cover the private-owner side. For the utility-scale version of the same trend, see Kern CRE’s coverage of the Euismod battery storage project near Rosamond.

Frequently asked questions

What did the Bakersfield City Council approve on Oct. 7, 2026?

An energy savings performance contract with Willdan Energy Solutions, not to exceed $7,990,188, for carport solar panels and a battery system at the city water site at 1000 Buena Vista Road.

How much does the Bakersfield solar and battery project cost?

The guaranteed maximum price is $7,990,188 and includes parking lot upgrades, a contingency and construction allowances. Staff put the best-case net cost at $4.4 million after about $3.5 million in incentives.

Will the project raise Bakersfield water rates?

Staff said no new money is needed. The project is part of the water enterprise fund’s capital program, which the city’s 2025 water rate study and Prop 218 process already covered. It does not use the general fund.

How much will the solar project save?

Staff projected about $382,000 in the first year and nearly $10.4 million from 2027 through 2041. The 9.5-year payback assumes the solar is energized by Dec. 31, 2027.

Why does the project need to be finished by the end of 2027?

About $2 million in solar incentives depends on that date. Under the 2025 federal budget law, solar projects that did not begin construction by July 4, 2026 must be in service by the end of 2027 to claim the federal investment credit.

Did the council reject this project before?

Yes. A version costing about $9.2 million was turned down Aug. 5, 2026, according to a Govly meeting summary. Staff then removed EV chargers and related work, cutting the first cost by $1.2 million.

Weighing solar, storage or power costs as part of an industrial lease or purchase in Kern County? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us.

Get Kern County CRE news monthly: subscribe to the Kern CRE report.

Sources

  1. City Council meeting video, Oct. 7, 2026 (3:30 and 5:15 p.m. sessions), public hearing item 8B, City of Bakersfield, Oct. 7, 2026.
  2. City Council agenda, Oct. 7, 2026, 5:15 p.m. meeting, item 8.b, City of Bakersfield, Oct. 7, 2026.
  3. Bakersfield City Council Meeting, August 5th, 2026 (meeting summary), Govly, Aug. 6, 2026.
  4. What the One Big Beautiful Bill Act means for the renewable energy industry, and how it can adapt, Bryan Cave Leighton Paisner, July 18, 2025.

About this article

Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.