Zone Change 24-0005 would bring a vacant, landlocked lot in line with the truck yards and warehouses around it. Here is what M-2 zoning allows and what still stands between the parcel and a building.
The Rosedale Highway industrial rezoning is City of Bakersfield Zone Change No. 24-0005, a request to rezone a vacant 2.99-acre parcel (APN 368-060-32) southeast of Rosedale Highway and Coffee Road, in Bakersfield, Kern County, California, from A (Agricultural) to M-2 (General Manufacturing). Landmark Survey and Engineering filed it for owner Beth Allison LLC, and no project is proposed. The city’s mitigated negative declaration circulated July 31 to Aug. 31, 2026. No hearing date has been announced.
Key takeaways
- Zone Change No. 24-0005 would rezone 2.99 acres at APN 368-060-32 from A (Agricultural) to M-2 (General Manufacturing). The general plan already designates the land SI (Service Industrial).
- The city’s mitigated negative declaration (MND) circulated for 30 days, July 31 to Aug. 31, 2026. Its seven mitigation measures cover air district rules, pre-construction wildlife surveys, cultural finds and regional transportation impact fees.
- Under Bakersfield’s code, M-2 allows any M-1 use, and M-1 allows any use permitted in the C-O, C-1 and C-2 commercial zones. The rezone would open the lot to industrial, service and commercial users.
- The city describes the parcel as vacant and landlocked from a public right-of-way, so access, not zoning, may be the bigger value question for a buyer.
- In Bakersfield, a zone change takes effect 30 days after the City Council’s second reading of the ordinance.
Zone Change 24-0005 at a glance
| Item | Detail |
|---|---|
| Project | Zone Change No. 24-0005 (ZC-24-0005): rezone from A (Agricultural) to M-2 (General Manufacturing); no development proposed |
| Location | Southeast of Rosedale Highway and Coffee Road, Bakersfield, CA 93308 (the initial study gives 7501 Rosedale Hwy.); City Council Ward 4 |
| Parcel | APN 368-060-32; about 2.99 acres; vacant; described by the city as landlocked from a public right-of-way |
| Applicant/owner | Landmark Survey and Engineering Inc. (applicant) for Beth Allison LLC (property owner) |
| Jurisdiction | City of Bakersfield, Development Services Department, Planning Division |
| Case numbers | ZC-24-0005 (also PP-ZC-24-0005); SCH 2026071050 |
| General plan | SI (Service Industrial), Metropolitan Bakersfield General Plan |
| Environmental review | Initial Study/Mitigated Negative Declaration; public review July 31 to Aug. 31, 2026 |
| Status | Comment period closed; no Planning Commission or City Council hearing date announced |
| Next step | Noticed Planning Commission hearing and recommendation, then City Council first and second readings of an ordinance |
What does the Rosedale Highway industrial rezoning change?
It would change the parcel’s zoning from agricultural to general manufacturing, matching how the land is already planned and used around it. Zone Change No. 24-0005 asks the City of Bakersfield to rezone about 2.99 acres. The city’s initial study and mitigated negative declaration says Landmark Survey and Engineering Inc. filed the request for property owner Beth Allison LLC for Assessor’s Parcel Number 368-060-32. It adds: “No project is currently proposed.”
The land is already planned for industry. The State Clearinghouse record lists its general plan designation as SI (Service Industrial) and describes the rezone as bringing the parcel into line with surrounding properties. The initial study concludes that, once rezoned, the site would be consistent with both the Metropolitan Bakersfield General Plan and the zoning ordinance.
Where is the parcel, and what surrounds it?
The parcel sits southeast of the Rosedale Highway and Coffee Road intersection. The initial study gives the address as 7501 Rosedale Highway, and the city’s notice of intent puts it in City Council Ward 4. CEQAnet lists State Route 58 and the BNSF main line as the nearby highway and railway.
The site is vacant and boxed in. The city describes “one vacant undeveloped 2.99-acre parcel surrounded by industrial warehouses and truck yards on all sides,” and says “the parcel is landlocked from access to a public right-of-way.” It sits in FEMA flood Zone X, a minimal-risk area, and “contains a plugged well.” The city’s documents do not say why the parcel kept agricultural zoning.
At the southwest corner of the same intersection, the proposed Riverview Marketplace would put a 405,531-square-foot, Whole Foods-anchored center on 46.16 acres that CEQAnet lists as zoned M-2. Its approvals include a general plan amendment but no zone change, according to the draft EIR record. Farther east, the Central Valley Renewables refinery upgrades at 6451 Rosedale Highway are in unincorporated Kern County under M-3 PD heavy industrial zoning.
What does M-2 zoning allow in Bakersfield?
M-2 allows heavy industrial uses plus everything permitted in the lighter M-1 zone, and M-1 in turn takes in commercial uses. Bakersfield’s industrial zones stack. Under Section 17.30.020 of the municipal code, M-2 allows “Any use permitted in the M-1 zone,” with no dwellings beyond accessory buildings. M-1 allows “Any use permitted in the C-O, C-1 and C-2 zones” under Section 17.28.020. So an M-2 lot can take office, retail and service users as well as heavy industry. Kern CRE’s overview of industrial zoning in Bakersfield and Kern County compares the zones citywide.
M-1’s own list covers contractor’s yards, warehouses, truck repair, and welding and fabrication shops. M-2 adds “Freighting and trucking yards and terminals,” truck stops and other heavy uses. The A zone, under Section 17.32.020, allows one home, crops, orchards, poultry and limited livestock.
| Zone | Typical permitted uses |
|---|---|
| A (Agricultural), BMC 17.32.020 | One single-unit dwelling, farmworker housing, crops, orchards, nurseries, poultry, limited livestock |
| M-1 (Light Manufacturing), BMC 17.28.020 | All C-O, C-1 and C-2 uses; contractor’s and building materials yards; warehouses; truck repair; machine, welding and fabrication shops |
| M-2 (General Manufacturing), BMC 17.30.020 | All M-1 uses; trucking yards and terminals; freight classification yards; truck stops; tire retreading; petroleum refining |
What does an M-2 rezone do to a small parcel’s value?
Under A zoning, a buyer with an industrial use would have to carry its own zone change, and the code bars permits for a use tied to a zone change until the ordinance takes effect (Section 17.64.100). The M-2 rezone completes that step and matches the parcel’s SI general plan designation.
Zoning does not fix access. The initial study’s list of later Public Works approvals includes right-of-way dedications, road improvement plans and encroachment permits. Until the lot has a recorded easement or dedication to a public street, it will price below a street-front yard, and the plugged well noted in the city’s documents is another discount factor. Kern CRE’s guide to buying industrial land covers entitlements and due diligence.
Conditions will travel with the land. The MND’s seven measures require:
- proof of air district compliance, including the Indirect Source Rule (Rule 9510), before grading;
- wildlife clearance surveys within 30 days of construction, with kit fox and nesting bird protocols;
- cultural resources training and stop-work rules; and
- payment of the Regional Transportation Impact Fee before building permits.
What did the traffic study test?
A Feb. 26, 2026 letter from Provost & Pritchard Consulting Group modeled a hypothetical 32,000-square-foot manufacturing building. It projected 137 daily trips, with 16 in the morning peak hour and 20 in the evening peak. Vehicle miles traveled came to 15.17 per employee, “8.04 percent higher than the significant threshold.” The letter recommended that the city “condition the project to have 11 charging stations installed.”
The MND’s mitigation list does not mention charging stations, so the staff report will show whether the city adopts that recommendation. For buyers, 32,000 square feet on 2.99 acres is about 25% coverage by our math, a useful marker of the building scale the review contemplated.
How is the Northwest Bakersfield industrial market doing?
Northwest Bakersfield availability runs slightly above the metro average, with lower asking rents. A national brokerage’s Q2 2026 Bakersfield industrial market report put Northwest Bakersfield availability at 10.4% with average asking rent of $0.65 per square foot per month, against 10.1% and $0.71 triple net (NNN) marketwide. NNN means the tenant pays taxes, insurance and maintenance. The report does not publish its submarket boundaries.
A regional brokerage report measured Bakersfield industrial vacancy at 9.55% in Q2 2026, down from 10.90% in Q1. It wrote that “specialized and flex properties maintain stronger occupancy and rental rates” than logistics buildings. Lots like this one price comp by comp, with access and utilities weighing heavily.
Who is behind Zone Change 24-0005?
The applicant is Landmark Survey and Engineering Inc. of Bakersfield, per CEQAnet. A business directory that mirrors state filings shows Beth Allison LLC as a California limited liability company formed Dec. 23, 2024, with a Bakersfield address. The company has not said whether it plans to build, sell or lease.
How does a zone change work in Bakersfield?
A zone change moves from application through CEQA review and a Planning Commission hearing to two City Council readings. The city’s zone change process handout lays out these steps:
- The applicant submits the application and fees, and the city deems it complete.
- CEQA review begins. Here, that was the MND, circulated July 31 to Aug. 31, 2026.
- The city notices a public hearing by newspaper, mail and on-site posting.
- The Planning Commission recommends approval, with or without conditions, or disapproval to the City Council.
- If the commission recommends approval, the council takes up a first reading and then a second reading of the ordinance. A disapproval can be appealed to the council.
- The zone change takes effect 30 days after the second reading.
What do the code and CEQA add?
The handout’s timeline appears to mark two stretches of about three months each, one leading up to commission action and one from council action to the effective date. Under Sections 17.64.070 and 17.64.100, a commission approval goes to the council without another noticed hearing unless there is an appeal or the council moves to deny, pick a more restrictive zone or change conditions. A commission denial that no one appeals is final.
After the city adopts an MND and files a notice of determination, challengers generally have 30 days to sue under Public Resources Code Section 21167. For pace, the city’s Zone Change 25-0001, a residential rezone, filed its MND in July 2025 and a notice of determination on Jan. 8, 2026.
What happens next for the Rosedale Highway rezoning?
A noticed Planning Commission hearing comes next, but no date has been announced. The comment period closed Aug. 31, 2026. The city’s notice says “the date, time, and place of future public hearings will be appropriately notified per City and CEQA requirements.” CEQAnet listed no agency comment letters on the filing, and no opposition has been reported.
The rezone is moving under the current general plan while the city drafts its Bakersfield 2045 General Plan, whose public review draft closed for comment Sept. 27, 2026. The city’s project page has the draft.
Frequently asked questions
What is Bakersfield Zone Change 24-0005?
It is a request to rezone a vacant 2.99-acre parcel, APN 368-060-32, southeast of Rosedale Highway and Coffee Road, from A (Agricultural) to M-2 (General Manufacturing). Landmark Survey and Engineering Inc. filed it for owner Beth Allison LLC. The general plan already calls the land Service Industrial, and no project is proposed.
What uses are allowed in M-2 zoning in Bakersfield?
M-2 allows everything permitted in M-1 plus heavier uses. Bakersfield Municipal Code Section 17.30.020 adds trucking yards and terminals, truck stops, tire retreading plants, railroad repair shops and petroleum refining. Dwellings are barred except accessory buildings. Because M-1 takes in commercial zones C-O, C-1 and C-2, M-2 land can host office and retail too.
What is the difference between M-1 and M-2 zoning in Bakersfield?
M-1 (Light Manufacturing, Section 17.28.020) covers commercial uses plus contractor’s yards, building materials yards, warehouses, wholesale businesses, truck repair, machine shops and welding. M-2 (General Manufacturing, Section 17.30.020) keeps all of that and adds heavy users such as freight yards, truck stops and refining. M-2 is the more permissive of the two.
Can retail go on M-2 land in Bakersfield?
On paper, yes. M-2 allows any M-1 use, and M-1 allows any use permitted in the C-O, C-1 and C-2 commercial zones. The proposed Riverview Marketplace, at the southwest corner of Rosedale Highway and Coffee Road, sits on 46.16 acres that state CEQA records list as zoned M-2, and its approvals call for a general plan amendment but no zone change. Site plan, parking and landscaping rules still apply.
How long does a zone change take in Bakersfield?
It depends on CEQA review and the hearing calendar. The steps are application, CEQA review, a noticed Planning Commission hearing and two council readings, with the change effective 30 days after the second reading. The city’s handout appears to mark two stretches of about three months, and special studies can add time. Zone Change 25-0001 ran from an MND filing in July 2025 to a notice of determination on Jan. 8, 2026.
When will the City Council vote on the Rosedale Highway rezoning?
No date has been announced. The Planning Commission must first hold a noticed hearing and make a recommendation. If it recommends approval and no one appeals, the council can adopt the ordinance in two readings without another noticed hearing.
Could the parcel be developed right after it is rezoned?
No. The code bars permits for a use tied to a zone change until the ordinance takes effect, 30 days after the second reading. A developer would then need grading and building approvals, would have to satisfy the MND’s measures and would pay regional transportation impact fees. Because the city calls the parcel landlocked, street access must also be solved.
Own, lease or want industrial land along Rosedale Highway, or weighing what a zone change could do for your parcel? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us to talk through uses, access and value. Get Kern County CRE news monthly: subscribe to the Kern CRE report.
Sources
- Zone Change No. ZC-24-0005, SCH 2026071050 (MND), CEQAnet (State Clearinghouse), received July 27, 2026.
- Initial Study/Mitigated Negative Declaration, Zone Change 24-0005, City of Bakersfield Development Services Department, signed July 27, 2026.
- Notice of Intent to Adopt a Mitigated Negative Declaration, Zone Change No. 24-0005, City of Bakersfield Planning Division, July 2026.
- Vehicle Miles Traveled (VMT) Analysis for a Zone Change for a Parcel Located South of Rosedale Highway, between Coffee Rd. and Wedding Ln. (APN 368-060-32), Provost & Pritchard Consulting Group, Feb. 26, 2026.
- Section 17.30.020, M-2 General Manufacturing Zone, Uses permitted, Bakersfield Municipal Code, current through Ord. 5223 (Aug. 26, 2026).
- Section 17.28.020, M-1 Light Manufacturing Zone, Uses permitted, Bakersfield Municipal Code.
- Section 17.32.020, A Agriculture Zone, Uses permitted, Bakersfield Municipal Code.
- Section 17.64.070, Zone changes: Hearing, Decision, Bakersfield Municipal Code.
- Section 17.64.100, Zone changes: Council action when planning commission decision not appealed, Bakersfield Municipal Code.
- Zone Change Process (handout), City of Bakersfield Development Services Department, Planning Division, undated.
- Beth Allison LLC, Bakersfield, CA: filing information, Bizprofile.
- Riverview Marketplace Commercial Project Draft EIR, SCH 2025101507, CEQAnet (State Clearinghouse), July 10, 2026.
- Site Plan Review 139, Map 102 (Central Valley Renewables LLC), SCH 2026070361 (NOE), CEQAnet (State Clearinghouse), received July 9, 2026.
- Regional brokerage market reports (Bakersfield industrial, Q2 2026).
- Regional brokerage market reports (Bakersfield industrial, July 2026).
- Zone Change No. 25-0001 (PP-ZC-25-0001), SCH 2025070683, project documents, CEQAnet (State Clearinghouse), MND July 16, 2025; NOD Jan. 8, 2026.
- Section 21167, time limits for CEQA actions, Justia (2025 California Code), 2025.
- General Plan: Bakersfield General Plan Update, City of Bakersfield (bakersfield2045.com).
- Title 17, Zoning (chapter index), Bakersfield Municipal Code.
About this article
Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.