Mojave Micro Mill Bonds: Kern Supervisors Back Up to $850 Million in Tax-Exempt Financing for Pacific Steel

The vote is a step federal tax law requires. The California Municipal Finance Authority, not the county, would issue the bonds for the rebar mill under construction between Mojave and Rosamond.

The Mojave Micro Mill bonds cleared Kern County supervisors 4-0 on Oct. 27, 2026. The board approved the federal tax-law step that lets the California Municipal Finance Authority issue up to $850 million in tax-exempt industrial development bonds for Pacific Steel Group’s rebar mill. County staff said Kern carries no financial liability.

Key takeaways

  • Kern County supervisors voted 4-0 on Oct. 27, 2026 to approve the TEFRA item for up to $850 million in tax-exempt industrial development bonds for Pacific Steel Group’s Mojave Micro Mill.
  • The California Municipal Finance Authority, not the county, would issue the bonds. County staff said Kern has no financial liability, and the agenda lists the fiscal impact as “None.”
  • Federal tax law requires an elected body where a privately used facility sits to approve the bonds after a public hearing before they can be tax-exempt.
  • The $850 million is a ceiling. Other public records put the mill’s cost at $630 million (2025) and committed capital at “more than $540 million” (October 2026).
  • Supervisors approved the 174-acre mill’s land-use permits on March 19, 2024, and construction began March 5, 2025. The Governor’s office said Oct. 19, 2026 that the mill is slated to open next year.

Mojave Micro Mill bonds at a glance

ItemDetail
ActionTEFRA hearing and resolution approving tax-exempt bond issuance
ResultApproved 4-0, Supervisor Leticia Perez not present (Oct. 27, 2026)
Bond ceilingNot to exceed $850,000,000
IssuerCalifornia Municipal Finance Authority (conduit issuer)
BorrowerPacific Steel Group
County fiscal impactNone (agenda)
Site860 Sopp Road, Mojave, per the agenda; 174 acres near Sopp Road and State Route 14
Project489,200-square-foot rebar mill plus 61,721 square feet of accessory buildings; 63-acre solar array
County land-use approvalMarch 19, 2024
ConstructionBegan March 5, 2025

What did Kern County approve for the Mojave Micro Mill?

Kern County supervisors approved the bond item 4-0 on Oct. 27, 2026. The agenda listed a hearing under the Tax Equity and Fiscal Responsibility Act (TEFRA) on “not to exceed $850,000,000 in tax exempt industrial development bonds by the California Municipal Finance Authority” on behalf of Pacific Steel Group “for construction of a steel micro mill located at 860 Sopp Road, Mojave.”

The recommended action was to open the hearing, take public comment, close the hearing, approve issuance of the bonds for TEFRA purposes and adopt a resolution. The agenda listed the fiscal impact to the county as “None.” The mill is in Supervisorial District 2.

The item started on the consent calendar, but the board chair announced at the start of the meeting that it had been removed and would be heard separately. It came up as the last item of the morning session. No one spoke during the public hearing, and Perez was not present for the vote.

County Treasurer-Tax Collector staff told the board that federal tax law requires approval from the government with jurisdiction over the project site for the bonds to be tax-exempt. Staff said the county will not be the issuer and has no financial liability for the bonds. The county’s debt advisory committee met Oct. 1 with representatives of the authority and Pacific Steel Group, found no deviation from county debt policies and concluded that the project offers a public benefit through local jobs and added recycling capacity, staff said.

According to staff, the bonds would pay for building and operating the mill and related infrastructure. The mill will make rebar from scrap metal, including shredded cars, appliances and structural and sheet metal.

What is a TEFRA hearing, and why did the county hold one?

A TEFRA hearing is the public hearing federal tax law requires before bonds that finance a private company’s facility can be tax-exempt. Under 26 U.S.C. 147(f), that approval can come from “the applicable elected representative” of a government where the facility sits, “after a public hearing following reasonable public notice.” A board of supervisors is one such elected body.

That was the role Kern’s board played. The bonds would be issued by the California Municipal Finance Authority, which describes itself as “acting as the conduit issuer” that gives qualified borrowers access to the tax-exempt market. The authority’s financing overview says eligible costs can include land, design, construction, equipment and legal fees.

The vote clears a required step. It does not set a sale date, interest rate or final amount, and none was stated at the hearing.

How does $850 million compare with the mill’s cost?

The agenda sets a ceiling of “not to exceed $850,000,000,” which is higher than other public figures for the project. A California Energy Commission grant notice, approved Jan. 21, 2025, describes “PSG’s planned $630,000,000” mill. In exchange for a $30 million California Competes tax credit, the company committed to “more than $540 million in capital investments,” according to the Governor’s office on Oct. 19, 2026.

Financing has shifted before. On May 1, 2025, The Bakersfield Californian reported that the company expected to close on a commercial loan to help fund the $630 million mill while it continued to work with the U.S. Department of Energy on federal financing.

Where does the Mojave Micro Mill stand?

The mill is under construction. Supervisors certified the mill’s environmental impact report and approved the project on March 19, 2024. The draft EIR describes a 489,200-square-foot mill with 61,721 square feet of accessory buildings and a 63-acre solar array on 174 acres near Sopp Road and State Route 14.

“Construction officially began March 5” in 2025, The Bakersfield Californian reported. The Governor’s office said Oct. 19, 2026 that the mill would produce “about 380,000 tons of seismic-grade rebar per year” and is “slated to open next year.” The same release said the mill “will bring 700 new jobs to Kern County.”

The county’s $3,375,000 Advance Kern job incentive was on the Sept. 29, 2026 agenda. For the site, permits and state incentives, see Kern CRE’s earlier report on the Mojave Micro Mill and its Advance Kern incentive.

What do the Mojave Micro Mill bonds mean for East Kern industrial real estate?

A financing approval signals a project is moving toward completion, and this one is large. The mill is an owner-user plant, so it adds no leasable space. Its market effect is more likely to come from suppliers, trucking and service firms that need yards and small shop buildings along the State Route 14 corridor.

For context, a national brokerage’s Q2 2026 Bakersfield industrial report put metro availability at 10.1%. That report covers the Bakersfield metro and does not break out Mojave or Rosamond. Kern CRE’s guide to reading an industrial market report explains the terms. East Kern’s energy build-out, from the Galaxy Solar project near Mojave to the Euismod energy storage project near Rosamond, is drawing similar interest in land near transmission.

Frequently asked questions

What did Kern County approve for the Mojave Micro Mill on Oct. 27?

Supervisors voted 4-0 on Oct. 27, 2026, with Supervisor Leticia Perez not present, to approve the TEFRA step for up to $850 million in tax-exempt industrial development bonds. The California Municipal Finance Authority would issue them for Pacific Steel Group’s Mojave Micro Mill. No one spoke at the public hearing.

Is Kern County paying for the Mojave Micro Mill bonds?

No, according to county staff. Staff told supervisors the county will not be the issuer and has no financial liability, and the agenda lists the fiscal impact as “None.” The authority would issue the bonds as a conduit issuer on behalf of Pacific Steel Group.

What is a TEFRA hearing?

It is the public hearing federal tax law requires before bonds that finance a private facility can be tax-exempt. An elected body where the facility is located, such as a board of supervisors, approves the bonds after reasonable public notice.

How much does the Mojave Micro Mill cost?

Public records differ. A 2025 Energy Commission notice cites $630 million, and the Governor’s office said in October 2026 that the company committed more than $540 million in capital investments. The bond ceiling is $850 million.

When will the Mojave Micro Mill open?

The Governor’s office said Oct. 19, 2026 that the mill is slated to open next year. Construction began March 5, 2025.

Where is the Mojave Micro Mill?

The mill sits on 174 acres near Sopp Road and State Route 14 in unincorporated Kern County, California, between Mojave and Rosamond. The Oct. 27 agenda lists the address as 860 Sopp Road, Mojave.

Need yard, shop or industrial space near the Mojave Micro Mill or along State Route 14? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us. Get Kern County CRE news monthly: subscribe to the Kern CRE report.

Sources

  1. Board of Supervisors regular meeting video, Oct. 27, 2026, 9 a.m. session, item 42, Kern County Board of Supervisors, Oct. 27, 2026.
  2. 26 U.S. Code 147(f): Public approval required for private activity bonds, Cornell Law School Legal Information Institute.
  3. How CMFA Financing Works, California Municipal Finance Authority.
  4. Electrified Steel Mill Long Duration Energy Storage Demonstration, Notice of Determination, SCH 2022100646, California Energy Commission (CEQAnet), approved Jan. 21, 2025.
  5. Mojave Micro Mill, Notice of Determination, SCH 2022100646, Kern County (CEQAnet), approved March 19, 2024.
  6. Mojave Micro Mill, Draft Environmental Impact Report, SCH 2022100646, Kern County (CEQAnet), Nov. 17, 2023.
  7. Governor Newsom spotlights California’s steel comeback: first new mill in 50 years brings jobs, investment, and cleaner industry, Office of Gov. Gavin Newsom, Oct. 19, 2026.
  8. Construction begins on Mojave steel mill, The Bakersfield Californian (via Tehachapi News), March 8, 2025.
  9. Pacific Steel Group prepares to forgo federal financing, The Bakersfield Californian, May 1, 2025.
  10. Bakersfield industrial market report, Q2 2026, national brokerage research, Q2 2026.

About this article

Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.