The permit only held a place in line for a license and never allowed construction. It ends Nov. 20, and the site on federal land near Rosamond then reopens to new applicants.
Nightfall Renewables Inc. has asked federal regulators to end its preliminary permit for the Maxwell Pumped Storage Project, a proposed 3,600-megawatt closed-loop hydropower plant on Bureau of Land Management land near Rosamond in Kern County, California. The Federal Energy Regulatory Commission’s Oct. 21, 2026 notice gives no reason. The permit stays in effect until Nov. 20, when the site reopens to new applicants.
Key takeaways
- Nightfall Renewables Inc. asked the Federal Energy Regulatory Commission (FERC) to terminate its preliminary permit for the Maxwell Pumped Storage Project (Project No. 15345), according to a FERC notice dated Oct. 21, 2026.
- FERC issued the permit on Oct. 11, 2024, and it would have run until Sept. 20, 2028. The notice states no reason for the surrender.
- As proposed in 2024, the closed-loop plant would have had 3,600 megawatts of capacity and produced about 14 million megawatt-hours a year, with four upper reservoirs on federal land and powerhouses about 5,000 feet underground.
- A preliminary permit only gives its holder priority to apply for a license. It never authorized construction or land disturbance.
- The permit stays in effect until the close of business on Nov. 20, 2026. New applications for the site can be filed after that.
- The plan called for a new substation on two Southern California Edison 500-kilovolt lines and a second line to SCE’s Whirlwind Substation, the grid hub tied to a large battery project west of Rosamond.
Maxwell Pumped Storage Project at a glance
| Item | Detail |
|---|---|
| Project | Maxwell Pumped Storage Project, FERC Project No. 15345 |
| Permit holder | Nightfall Renewables Inc. (Roseville) |
| Action | Request to terminate the preliminary permit |
| FERC notice | Dated Oct. 21, 2026; scheduled for Federal Register publication Oct. 26 (91 FR 67310) |
| Permit term | Issued Oct. 11, 2024; would have expired Sept. 20, 2028 |
| Permit ends | Close of business Nov. 20, 2026 (30 days after the notice) |
| Location | Bureau of Land Management land near Rosamond, Kern County |
| Size as proposed | 3,600 MW closed loop; about 14 million MWh a year (2024 filing) |
| Grid tie as proposed | New Maxwell Substation on two SCE 500-kV lines; second line to SCE Whirlwind Substation |
| Reason given | None |
What happened to the Maxwell Pumped Storage Project?
Nightfall Renewables Inc., the permit holder, “has requested that its preliminary permit be terminated,” according to FERC’s notice dated Oct. 21, 2026. The notice was filed with the Federal Register on Oct. 23 and is set for publication Oct. 26.
FERC issued the permit on Oct. 11, 2024, and it would have expired on Sept. 20, 2028. The project “would have been located on lands administered by the U.S. Department of the Interior, Bureau of Land Management near the unincorporated town of Rosamond in Kern County, California,” the notice says.
The one-paragraph staff notice gives no reason for the request and sets no public comment period.
What was planned near Rosamond?
Nightfall filed for the preliminary permit on Feb. 26, 2024. It proposed to study a 3,600-megawatt closed-loop pumped storage plant on federal land near Rosamond, according to FERC’s June 2024 notice accepting the application. The company estimated annual production at about 14 million megawatt-hours.
Pumped storage works like a large battery. Water is pumped to an upper reservoir when power is plentiful and released through turbines to a lower reservoir when power is needed. In a closed-loop system, the reservoirs are not connected to a river or other outside body of water, according to the U.S. Department of Energy.
The 2024 filing described four upper reservoirs of about 24.3 to 29.1 acres each, holding roughly 2,385 to 2,760 acre-feet apiece at elevations of 4,720 to 5,120 feet. It also called for 36 lower reservoirs excavated from rock and 12 powerhouses about 5,000 feet below the surface.
For the grid connection, a new Maxwell Substation would have tapped two existing Southern California Edison 500-kilovolt lines. A second line would have run to SCE’s Whirlwind Substation, and a new 3.5-mile, 500-kilovolt line would have reached the powerhouses.
What does a FERC preliminary permit allow?
A preliminary permit reserves a developer’s place in line and nothing more. “The sole purpose of a preliminary permit is to grant the permit holder priority to file a license application during the permit term,” FERC wrote in its 2024 notice. The permit does not authorize land-disturbing activities.
Building the plant would have required a FERC license, a separate and much longer review, along with federal approval to use the land. The 2026 notice describes the project only as one that “would have been located” near Rosamond.
When does the permit end, and can someone else apply?
The permit stays in effect until the close of business 30 days from the notice date, which is Friday, Nov. 20, 2026. If FERC is closed that day, the permit runs through the next day the commission is open.
“New applications for this site may not be submitted until after the permit surrender is effective,” the notice says. After that, another developer could seek its own preliminary permit for the site, and FERC would publish notice of any new application in the Federal Register.
What does the Maxwell Pumped Storage Project surrender mean for Rosamond and East Kern land?
Little changes on the ground. The permit covered federal land, allowed no construction and was not a Kern County land-use approval. The federal notices tie no county case to it.
What stays is the reason a developer looked here: transmission. SCE’s Whirlwind Substation west of Rosamond is also the grid connection for the proposed Euismod Energy Storage Project, a 1,150-megawatt battery plan that was on the Kern County Planning Commission’s Oct. 22 agenda. How long a project waits for power is its own question, covered in Kern CRE’s guide to SB 410 energization timelines. The state rules that govern those battery sites are summarized in the battery energy storage regulations guide, and a nearby city-backed project is covered in Bakersfield’s solar and battery approval.
For owners of land near Whirlwind and along the SCE 500-kilovolt corridor, energy interest is real, but a preliminary permit is a place in line, not a project. Leases, county approvals and interconnection agreements are what put a number on land value. The Maxwell site reopens to new applicants after Nov. 20.
Frequently asked questions
What was the Maxwell Pumped Storage Project?
A proposed 3,600-megawatt closed-loop pumped storage hydropower plant on federal land near Rosamond, studied by Nightfall Renewables Inc. under FERC Project No. 15345. FERC’s 2024 notice put its output at about 14 million megawatt-hours a year.
Why did Nightfall Renewables give up the permit?
FERC’s notice dated Oct. 21, 2026 gives no reason. It says only that the company asked for its preliminary permit to be terminated.
When does the Maxwell preliminary permit end?
At the close of business on Nov. 20, 2026, or the next business day if FERC is closed. The permit had been set to expire Sept. 20, 2028.
Was any construction approved near Rosamond?
No. A preliminary permit gives priority to apply for a FERC license and does not allow land disturbance. The federal notices tie no Kern County approval to the project.
Can another company propose pumped storage at the site?
Yes, once the surrender takes effect. FERC’s notice bars new applications for the site until then.
What is closed-loop pumped storage?
It stores electricity by moving water between two reservoirs that are not connected to a river or other outside water source. Pumps lift the water uphill when power is cheap, and turbines run on it when power is needed.
Own land near Rosamond or along East Kern’s transmission lines and fielding energy inquiries? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us. Get Kern County CRE news monthly: subscribe to the Kern CRE report.
Sources
- Nightfall Renewable Inc.; Notice of Surrender of Preliminary Permit (FR Doc. 2026-21768, 91 FR 67310), Federal Energy Regulatory Commission, dated Oct. 21, 2026; Federal Register publication Oct. 26, 2026.
- Nightfall Renewables Inc.; Notice of Preliminary Permit Application Accepted for Filing (FR Doc. 2024-13285), Federal Energy Regulatory Commission, June 17, 2024.
- Pumped Storage Hydropower, U.S. Department of Energy, accessed Oct. 24, 2026.
About this article
Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.