Shafter Utility Undergrounding: City Council Waives Lerdo Highway Power Line Requirement for Floyd’s Store

The council waived the rule with no in-lieu deposit. The store must still bury the electric service to its building.

The Shafter City Council voted 4-0 on Nov. 3, 2026, to waive Shafter utility undergrounding rules for the Floyd’s Store relocation on Lerdo Highway in Shafter, Kern County, California. The store no longer has to bury the overhead PG&E distribution lines along its frontage, a job its appeal put above $500,000.

Key takeaways

  • The council granted an appeal by Richard N. Reese Family LLC under Shafter Zoning Ordinance Section 10.380. It waived the requirement to bury the existing overhead electrical distribution lines along the Floyd’s Store frontage on Lerdo Highway. The vote was 4-0.
  • The waiver carries no deposit in lieu of the waived work. City staff said the store must still underground the electric service to its building.
  • The appeal letter puts the cost to bury the frontage lines at more than $500,000. The store had already spent about $160,000 on electrical conduit work along the highway.
  • Staff said the waiver has no immediate fiscal impact on the city. It would shift the cost to the city if Shafter later buries that stretch of Lerdo Highway.
  • Staff said one of the next applications under the rule is a commercial property on Seventh Standard Road west of Gossamer Grove Boulevard.

Floyd’s Store undergrounding waiver at a glance

ItemDetail
DecisionWaiver of the frontage utility undergrounding requirement, granted
Body and dateShafter City Council, Nov. 3, 2026 (Management Report 2)
Vote4-0; motion by Council Member Prout, second by Council Member Espinoza
AppellantRichard N. Reese Family LLC, applicant and property owner, for Floyd’s Store
SiteFloyd’s Store relocation, south side of Lerdo Highway, Shafter
RuleShafter Zoning Ordinance Section 10.380; appeal under subsection 7
What was waivedUndergrounding of the existing overhead electrical distribution lines along the project frontage
Still requiredUnderground electric service to the building, under PG&E’s standard requirements
In-lieu depositNone
Cost cited in the appealMore than $500,000 for the frontage lines, plus about $160,000 already spent on conduit work
Reason for the moveThe California High-Speed Rail project is taking the existing store location, per the appeal letter
City cost effectNone immediately; future undergrounding of that stretch would fall to the city, per staff

What did the Shafter City Council decide on Floyd’s Store?

The council granted the appeal and waived the requirement to bury the overhead distribution lines along the store’s Lerdo Highway frontage. The Nov. 3 agenda described the request as a waiver “without a deposit in lieu of the waived work.”

Council Member Prout moved to grant the waiver, and Council Member Espinoza seconded. The motion passed 4-0 on a roll-call vote. Staff called it a project-specific waiver that needs no in-lieu deposit. The requirement to bury the electric service to the building stays, subject to PG&E’s standard requirements.

Why did Floyd’s Store ask Shafter for the waiver?

The store is moving because “the California High-Speed Rail project is taking the existing location,” according to the appeal letter dated Oct. 26, 2026, which is attached to the agenda item. The letter says the business faces a “government-imposed relocation timeline” and that “PG&E has given notice of project delays.” For background on the rail project, see Kern CRE’s coverage of the Bakersfield high-speed rail station shift.

The letter puts “the estimated cost to underground the existing frontage distribution lines” at more than $500,000. That comes on top of about $160,000 Floyd’s has already spent on conduit work along the highway. It describes the frontage lines as major electrical distribution facilities serving the surrounding area, not service lines dedicated to Floyd’s.

The letter also says nearby owners have had to bury only the service lines to their own properties. “To our knowledge, Floyd’s would be the only developer required to underground these major lines, on the south side of the highway, along the approximately 8.8-mile corridor from State Route 99 to downtown Shafter,” it says. The appellant offered instead to run underground service from the existing pole to the store, subject to PG&E authorization.

At the council’s Oct. 20 meeting, the applicant put PG&E’s quote to bury the poles at more than $530,000 and the total cost at about $600,000.

What is the Shafter utility undergrounding rule in Section 10.380?

Section 10.380 of Shafter’s zoning ordinance requires developers to place new and existing utilities within a project’s boundary underground at their own expense. City staff told the council on Oct. 20 that the rule works much like street, curb, gutter and landscaping frontage improvements, and that it dates to the zoning ordinance the city adopted in 1996.

Subsection 7 lets an applicant appeal to the City Council for a waiver of all or part of the requirement. The grounds are “topographic conditions, soil or other factors” that make undergrounding unreasonable or impractical, as staff and the city attorney described it at both meetings.

On Oct. 20, staff said Lerdo Highway is being discussed as a gateway to the city and that the council’s decision “will set the expectation and standard for all the future development” there. Staff also said the ordinance was likely “not consistently applied in the past” and that adding exemptions would take a code amendment.

Who pays if Shafter buries the Lerdo Highway lines later?

The city would. Staff told the council on Nov. 3 that the waiver has no immediate fiscal impact but would shift the cost to the city if the council later pursues an undergrounding project along Lerdo Highway. The city attorney said that when the city does not require an applicant to do the work, burying that utility becomes the city’s responsibility and cost.

A council member asked what message the requirement sends “to other businesses that might want to come to Shafter” and asked about grants or a capital project to pay for undergrounding. The city manager said the cost of the infrastructure “has never been a bar for a business coming in.” During public comment, one speaker supported undergrounding along Lerdo Highway, calling it a major corridor for the city.

Could other Shafter projects get the same waiver?

Yes, if they meet the standard. Staff said the appeal in the code is open to any business that meets it. One of the next applications is a commercial property on Seventh Standard Road west of Gossamer Grove Boulevard, behind the city’s police substation.

At the Oct. 20 meeting, a council member said projects in the Mission Lakes Specific Plan area along 7th Standard Road must follow the undergrounding rule. Kern CRE covered that plan in its report on the Mission Lakes development agreement. On Nov. 3, a council member said the council may review the undergrounding policy in January. No date has been set.

How does PG&E’s Rule 20 handle undergrounding in California?

PG&E’s Electric Rule No. 20, approved by the California Public Utilities Commission, sets out how the utility replaces overhead lines with underground lines. It is separate from city development rules.

Under Rule 20A, PG&E pays for conversions that a city or county finds are in the general public interest after public hearings, such as along arterial streets or heavily traveled roads, inside an underground district the local government creates by ordinance. The tariff says PG&E stopped allocating new Rule 20A work credits after Dec. 31, 2022, and that unused credits expire after Dec. 31, 2033.

Under Rule 20B, applicants pay for the trenching, conduit and other substructures, plus any amount by which the underground system costs more than a new equivalent overhead system. The project must cover both sides of a street for at least one block or 600 feet, whichever is less. Under Rule 20C, an applicant pays in advance the estimated cost of the underground facilities, less the net salvage value and depreciation of the overhead lines being replaced.

Utility timelines and costs also shape site plans for industrial users. Kern CRE’s guides to industrial building power requirements and SB 410 energization timelines cover both.

What happens next for the Floyd’s Store relocation?

Staff will update the project’s conditions to reflect the waiver, and the undergrounding of the service line to the building stays in the conditions. The appeal letter asked for prompt action so that “electrical service and occupancy approvals can proceed on the High-Speed Rail relocation schedule.”

On Oct. 20, a recommendation read into the record directed staff to look at alternatives and revisions to determine whether more exemptions to Section 10.380 are warranted. No amendment to the section was on the Nov. 3 agenda. Developers weighing Shafter sites can also review how the city treats land use in Kern CRE’s guide to industrial zoning in Bakersfield and Kern County.

Frequently asked questions

What did Shafter decide about Floyd’s Store and the Lerdo Highway power lines?

On Nov. 3, 2026, the Shafter City Council voted 4-0 to waive the requirement that the Floyd’s Store relocation bury the existing overhead PG&E distribution lines along its Lerdo Highway frontage. The waiver carries no in-lieu deposit.

Why is Floyd’s Store relocating in Shafter?

Its appeal letter says the California High-Speed Rail project is taking the store’s existing location. The new store sits on the south side of Lerdo Highway.

How much would burying the Lerdo Highway lines have cost?

The appeal letter estimates more than $500,000 for the frontage distribution lines, on top of about $160,000 already spent on conduit work. At the Oct. 20 meeting, the applicant put PG&E’s quote at more than $530,000.

Does Floyd’s Store still have to put any lines underground?

Yes. City staff said the requirement to bury the electric service to the store’s building remains, subject to PG&E’s standard requirements.

What is Shafter Zoning Ordinance Section 10.380?

It is Shafter’s utility undergrounding rule. Staff described it as requiring new and existing utilities inside a project’s boundary to go underground at the developer’s expense. Subsection 7 allows an appeal to the City Council for a waiver when topographic conditions, soil or other factors make that unreasonable or impractical.

Who pays if Shafter buries Lerdo Highway lines in the future?

The city. Staff said the waiver shifts that cost to Shafter if the council later pursues an undergrounding project along the highway.

Looking at retail, commercial or industrial sites in Shafter? Call Kern CRE at 855-KERN-CRE (855-537-6273) or contact us. Get Kern County CRE news monthly: subscribe to the Kern CRE report.

Sources

  1. City Council regular meeting video, City of Shafter, Nov. 3, 2026.
  2. City Council regular meeting agenda, Management Report 2: Floyd’s Store appeal and request for waiver of frontage utility undergrounding requirements on Lerdo Highway, City of Shafter, Nov. 3, 2026.
  3. Appeal and Request for Underground Utility Waiver, Floyd’s Store relocation on Lerdo Highway, Richard N. Reese Family LLC (attached to the Nov. 3 agenda item), Oct. 26, 2026.
  4. City Council regular meeting video, discussion of Zoning Ordinance Section 10.380, City of Shafter, Oct. 20, 2026.
  5. Electric Rule No. 20, Replacement of Overhead with Underground Electric Facilities, Pacific Gas and Electric Company, effective July 10, 2023.

About this article

Kern CRE prepared this article with help from AI research and writing tools. An editor reviewed the draft, checked its facts against the sources linked above and edited it for accuracy and clarity. Details come from public records and the sources cited; unless stated, Kern CRE and ASU Commercial were not involved in the transaction or project.